Exciting news: The entire UV Pilot system was successfully run on Monday, June 2nd, during the day and through the night.
On Tuesday morning, a significant amount of seaweed had accumulated over the weir wall during high tide, which we believe may be related to the recent Nor’easter, leading to clogged pumps. As such, the system has been paused. Thanks to quick action, Sunbelt successfully cleaned the pumps and piping.
We have temporarily paused the system's restart as we work to develop an effective solution for the seaweed issue, which our consultants hope to have in the next day or so, working closely with Sunbelt, the Lynn Water and Sewer Commission, and the Town of Swampscott.
|