As of June 10, pumping of sand (an estimated total of 755,000 cubic yards) onto South Beach is complete. Their contractor, Marinex Construction, Inc., will now begin the demobilization process.
During demobilization, Marinex will remove offshore pipe, level vehicle tracks along the beach, and level out any significant areas of scarping (steep or uneven areas) along the renourished areas from Beach Marker 8 to Beach Marker 27. Below is the timeline (weather permitting):
- All beach access locations will reopen by Saturday, June 13
- Metal and HDPE pipe will be staged between Beach Markers 9 and 10 by Monday, June 14
- Tilling of South Beach will begin on Tuesday, June 16 (estimated 1-2 days to complete)
- All contractor equipment should be gone by the end of June
To learn more and track the project's progress, visit the Town's project page here.
|