PHASING PLANS
The Value of Strategic Phasing: Why an Additional Mobilization Can Be a Cost-Effective Move
Shutting an entire site down to save on move charges may be reduce your proposal pricing (be sure to look for # of 'moves' when comparing bids), but for a retail center or an HOA community, that can cause more than just angry tenants, patrons, and residents.
For a retail center, you could face a breach of contract when you don't provide reasonable access during construction and tenants may present "Lost Profit" claims. Disrupted businesses can suffer real financial damages such as a popular drive through being blocked off during the big lunch rush.
Project phasing needs to work around these critical hours to keep operations moving. Be sure your contractor has factored in phasing out the work into sections of your property so reasonable access is maintained, and has provided detailed site maps and phasing plans so you clearly know what to expect.
While each move in charge can start around $2,500 (seal crews) to $8,500+ (asphalt paving crews) to cover the travel time, equipment costs and labor rates for each move, that investment can produce immeasurable value to business operations and residential communities in the long run; and should be accounted for as an important part of the budget.
Also, remember, the earlier you show consideration and communicate:
- The phasing plans (with dates each area will be addressed, available entry/exit points, and nearby parking), the more support and cooperation you will receive.
|