Projects supported by properly completed permit applications submitted before the effective date may remain governed by the Eighth Edition (2023) for the life of the permit and any valid extension, even if permitting or construction continues into 2027.
With the Ninth Edition scheduled to take effect on December 31, 2026, developers and property owners should review the status of pending projects and consult with the project architect whether the updated requirements may affect their plans, specifications, and permitting schedules.
Similarly, for projects approaching permit submission, developers should coordinate with their architects, engineers, and permit expediters to determine whether submission under the Eighth Edition is feasible and appropriate. Particular attention should be given to energy compliance, mechanical systems, roofing assemblies, product approvals, and flood-related requirements.
Developers should also confirm the applicable submission requirements with the local building department for the particular municipality the subject property is located in, particularly where applications are incomplete, nearing expiration, or expected to undergo substantial revisions.
Although an earlier submission may allow a qualifying project to proceed under the existing code, the decision to expedite should be made project by project. Early coordination with design professionals and building officials may help identify revisions, avoid permitting delays, and limit added construction costs.
As always, our team at Bercow Radell Fernandez Larkin and Tapanes is available to assist developers, property owners, and project teams in evaluating how the Ninth Edition may affect pending and future projects, coordinating with design and permitting professionals, and navigating applicable submission deadlines and local government requirements.
|