Crews begin the next phase of Two Rivers’ effort to remove lead service lines.
Work has officially begun on the 2026–2027 Lead Service Lateral (LSL) Replacement Project in Two Rivers. This project focuses on replacing older lead water service lines to help ensure safe and reliable drinking water for our community. The City’s contractor, Essential Sewer and Water, mobilized back into Two Rivers a few days ago and began replacing water services (both the public and private portions) on Tuesday, March 3.
Construction has started in these areas:
- 24th Street between the East Twin River and Lincoln Avenue
- Emmet Street from 22nd Street south to 17th Street
Over the next few weeks, crews will continue moving through nearby streets as service replacements progress throughout the project area.
Residents in active construction zones may notice temporary traffic disruptions, construction equipment, and brief water service interruptions when individual services are replaced. Property owners will receive direct coordination from the contractor when work is scheduled at their specific property.
This work is part of the City’s ongoing effort to remove lead service lines from the water system and comply with Wisconsin Department of Natural Resources requirements, ensuring safer drinking water for current and future residents.
City Fact: Since 2017, the City of Two Rivers has replaced more than 1,000 lead service laterals, making steady progress toward eliminating lead from the community’s water infrastructure. Another 300 services will be replaced in 2026-2027
|