Site work continues
Northeast Earth Mechanics, the contractor the City hired in 2023, has been forging ahead with public improvements including public and private underground utilities public, and the base layer of roadway pavement.
Shoreland stabilization is underway with Northeast Earth Mechanics constructing a stone toewall along the Cocheco River shoreline. This innovative and sustainable vegetated wall system involves soil and vegetation planted in a mesh bag. This vegetation roots into existing soils through the bag, stabilizing the shoreline soils, allowing them to adapt and move with changing climate and weather conditions and endure storm surges and ice events.
Behind the seawall, you can see the beginnings of Nebi Park, the three-plus acre public green space that will be available for all to enjoy access to the river. The centerpiece is the park pavilion. The foundation has been dug, ground supports inserted, and the building will be constructed in 2025.
Challenges
Along with all this progress, there have also been some bumps. The soils and unknown urban debris buried on site have posed problems, creating some unanticipated costs for the project which were unforeseen. For 200 years the site has been used in a more industrial manner. The mill foundations, debris, and the infrastructure of the former wastewater treatment plant have lifted the level of unexpected issues above the anticipated costs of the project.
The public portions of the project are still on track for a spring 2026 completion. The costs to accomplish this though, is challenging. We achieved some savings by consolidating kayak launches to the paddle sports dock, and we were able to reuse some existing water mains instead of replacing them. The Cochecho Development Waterfront Advisory Committee and its Parks Subcommittee are working to ensure Nebi Park and the park pavilion are constructed as close to the community-envisioned plan as possible.
|