Crews continue to demolish sidewalks and gutters along US-95 from 6th Avenue to north of 7th Avenue in Payette.
Paving north of 7th Avenue was paused last week to accommodate traffic from the closure on SH-55. It is is expected to finish this Tuesday. Once done, crews will begin paving US-95 between 24th St and 16th Ave in Fruitland. Paving will stop before the intersection.
What to expect in Payette:
- Reduced to one lane with temporary signals directing traffic at NE 10th Ave and 6th Ave
- 35 mph speed limit in work zone
- Delays, allow extra time and consider an alternate route
|