What's Happening?
The contractor has successfully completed all water main improvements. Remaining activities include roadway resurfacing, pavement striping and restoration of the entire project area to its pre‑construction condition.
Beginning October 26 and continuing through November 2, 2026, the contractor will mill and resurface the roadway at multiple locations simultaneously. Roadway milling is expected to take approximately one day to complete, followed by roadway resurfacing and temporary striping, which will take an additional 2–3 days across all areas. Below is a list of each activity and the associated traffic impacts:
|