Paving and preservation work is moving steadily across Washington County, with all major treatments on track for completion by late July and early fall.
Here’s a quick snapshot of where things stand:
-
Chip Seal – In Progress
Crews are moving road by road and expect to finish by late July.
-
Asphalt Overlay – Ongoing Through Summer
Overlay paving is advancing across several corridors and will continue into early fall.
-
Crack Seal – Currently Underway
Crack sealing is moving through neighborhoods and rural segments and is expected to wrap up later this month.
-
Slurry Seal – Beginning Next Week
Slurry seal application starts July 20, following crack seal completion.
Residents may see brief delays, lane closures, or short-term neighborhood access restrictions as crews move through each area. Thank you for your patience while we complete this important seasonal maintenance.