The City of Henderson has been prompted to revise the backbone water infrastructure planning for West Henderson. This action was taken to address shortfalls in the collection of revenues from the assessment of West Henderson Phase 1 Water Backbone Infrastructure rates, significant reductions in water usage anticipated from future developments within West Henderson, and the initiation of the Southern Nevada Water Authority Horizon Lateral project.

Effective January 1st, 2023, the rates charged to existing or future projects benefitting from the water backbone infrastructure will be increased. Approved rates effective as of January 1, 2023, are listed below: 
             
  • 2630 PZ water infrastructure rate: $3,527 per EDU
  • 2760 PZ water infrastructure rate: $5,660 per EDU 

Changes to the Commercial and Industrial Meter Equivalency Chart were also approved. Effective 1/1/2023, the following equivalency applies: