Upcoming Work:
-Excavation and installation of watermain began on Wednesday morning near the intersection of STH 19 and was completed up to Lake Circle intersection.
Work Anticipated This Week:
- Contractor to continue watermain from the intersection of Lake Circle to the north.
- The contractor will be shutting down the road near the intersection of Lake Circle and CTH CV to install utilities across the roadway around the middle of the week. Once the crossing is completed, the contractor will continue to work along the east edge of the roadway to allow local and business traffic through.
- A second utility crew is slotted to be on site August 4,and they will be working south of Lake Windsor 2025.
|