Woodland Avenue Waterline and City of Palo Alto Interconnect
Construction work for the Woodland Avenue waterline and City of Palo Alto emergency intertie project began. The City’s Contractor, Golden State Construction & Utility Inc., is preparing for the tie-in at Scofield and Woodland.This project would establish an emergency intertie with the City of Palo Alto’s water system. Establishment of interties will allow the City to obtain emergency water in case the City’s connection with the Hetch Hetchy Aqueduct is severed. Currently, the City has no emergency source of water if the City’s connection with the Hetch Hetchy Aqueduct is severed. Additional information on the project, including the plan set, can be found on the City website:
https://www.cityofepa.org/publicworks/project/woodland-avenue-waterline-and-city-palo-alto-interconnect-project
University Ave & Weeks St 12-inch Water Main Project:
Construction for the University Avenue & Weeks Street Watermain project is underway. The Weeks Street portion was recently completed and now the contractor is continuing installation of the new 12" water main active on Cooley and University Avenue. The crew is actively working on service lateral connections on Cooley and Weeks Street work including abandoning the existing water main, concrete restoration, and asphalt restoration. Additional information on the project, including the plan set, can be found on the City website:
https://www.cityofepa.org/publicworks/project/university-avenue-and-weeks-street-12-water-transmission-main-project
General Utility Information:
If you need help regarding spills, overflows, or any emergency services and other information: West Bay at (650) 321-0384.
All other calls regarding applications, permitting, projects or other: EPASD at (650) 325-9021.
Additionally, the West Bay web site for further service information: https://www.westbaysanitary.org/your-sewer-guide.
Encroachment Permits Issued and Underway
o Permiso PW2024-0105 ubicado en 95 Newell Rd a ser completado antes del 01/16/2025 por Broadband.
o Permiso PW2024-0115 ubicado en 660 Donohoe St a ser completado antes del 02/10/2025 por Langan.
o Permiso PW2024-0116 ubicado en 2411 Pulgas Ave a ser completado antes del 02/13/2025 por EHP.
o Permiso PW2024-0118 ubicado en 45 Newell Rd a ser completado antes del 02/17/2025 por A Plus Tree.
o
AT&T
o Permiso PW20244-0088 ubicado en 1671 Woodland Ave a ser completado para 12/15/2024 (Nextedge).
o Permiso PW2024-0104 situado en 1890 Bay Rd que se completará antes del 02/04/2025.
o Permiso PW2024-0124 situado en 2560 Pulgas Ave que se completara antes del 03/16/25. Permiso PW2024-0123 situado en varios lugares cerca de 901 Weeks St por 03/16/2025.
o Permiso PW2024-0125 situado en 1877 Bay Rd que se completara antes del 03/16/2025.
· Permisos de invasión emitidos
Los siguientes permisos de PG&E implican trabajo eléctrico para reemplazar una cruceta rota en un poste eléctrico existente. Habrá control de tráfico en estas áreas:
o PW2024-0061 en 796 Bell St a completer antes 12/18/2024.
o PW2024-0089 en 934 O’Connor St a completer antes 12/15/2024.
o PW2024-0094 en 2292 Glen Way a completer antes 12/23/2024.
o PW2024-0096 en 1108 Bay Rd a completer antes 12/23/2024.
o PW2024-0097 en 280 Verbena Dr a completer antes 01/02/2025.
o PW2024-0098 en 1686 Michigan Ave a completer antes 01/02/2025.
o PW2024-0099 en 207 Azalia Dr a completer antes 01/02/2025.
o PW2024-0091 en 1064 Beech St a completer antes 12/22/2024.
o PW2024-0092 en 216 Gardenia Wy a completer antes 12/22/2024.
o PW2024-0093 en 2231 Euclid Ave a completer antes 12/23/2024.
o PW2024-0095 en 132 Azalia Dr a completer antes 12/23/2024.
o PW2023-0069 en 952 Beech St a completar antes del 02/18/2025.
o PW2024-0119 en 1928 Cooley Ave a completar antes del 02/17/2025.
|