KINGS & VICTORY UPDATE
Crews have made significant progress over the past two weeks. Work in front of Endeavor Elementary continues - we appreciate the patience of parents and school staff during construction! Work in front of the school should have a level grade of gravel on Friday, October 28.
COMING UP: The grading crew is adding base materials to the main sections of the roundabout in preparation for asphalt on November 8. Crews will also be focused on the west section (subbase/base materials, sidewalk, curb and gutter, splitter island, etc.) in preparation for paving.
Citizens are encouraged to watch out for construction activities in the work zone as changes occur every day.
|