CONSTRUCTION UPDATE

Weeks of October 26 and November 1, 2026

Crews are actively working on several improvements along the corridor, including rebuilding sidewalks, driveways, and curbs, installing storm drains and utilities, and preparing for new streetlight and traffic signal foundations. These activities will continue over the next several weeks and may result in temporary impacts to driveways and pedestrian routes. Access to businesses and residences will be maintained.


Work will generally occur Monday through Friday during daytime hours (6:00 a.m. to 4:00 p.m.), with intermittent nighttime work (6:00 p.m. to 6:00 a.m.). Intermittent lane closures will take place along the project corridor, with at least one lane remaining open to traffic at all times. 

Construction crews excavating for utility installation at the Foothill & Rochester Station.

All construction is dynamic and the schedule is subject to change. Visit the project Google Map for the most up-to-date scheduled closures and available detour routes.



Si prefiere recibir información de construcción en español, llame al (877) 55-SBCTA.

POMONA TRANSIT CENTER

Construction activities at the Pomona Transit Center are anticipated during the week of October 26 and will include formwork, concrete pouring, and installation of new station equipment and systems. Increased noise levels may occur in the surrounding area during this work.



This work is not anticipated to impact the Pomona Transit Center’s schedule.

CENTER-RUNNING STATIONS

Construction is underway at the future West Valley Connector center-running stations along Holt Boulevard in Ontario. In the coming weeks, crews will continue work at the following locations:



  • Center-Running Station at Campus Avenue
  • Center-Running Station at San Antonio Avenue
  • Center-Running Station at Mountain Avenue


Work will include installation of station canopies and electrical equipment, construction and finishing of concrete bus pads and curbs, paving, and accessibility improvements. Crews will also continue landscaping and irrigation work at some station locations.


Pedestrian access will be maintained throughout construction. There may be construction equipment, increased truck activity, and noise near the work areas. Work activities may shift as construction progresses.

SIDE-RUNNING STATIONS

Outside lane closures are underway at the future station locations listed below. At least one lane will remain open to traffic at all times. Construction activities will include demolition of any current stations, roadway demolition, utility relocation, and construction of bus pads and new stations.


Pomona

  • EB Garey Avenue at Holt Boulevard


Ontario

  • Ontario Mills
  • Ontario Airport at Terminal 2 and Terminal 4
  • EB and WB Inland Empire Boulevard at Porsche Way


Rancho Cucamonga

  • Rancho Cucamonga Metrolink Station
  • EB and WB Milliken Avenue at Foothill Boulevard
  • EB and WB Rochester Avenue at Foothill Boulevard
  • Day Creek Boulevard at South Main Street (Victoria Gardens)


Pedestrian access will be maintained throughout construction, and no interruptions to bus operations are anticipated while this work is underway.

For information regarding Omnitrans bus service during construction, please visit Omnitrans.org.

WEST VALLEY BUSINESS CONNECTOR PROGRAM

This Week's Business Highlight:

This week’s business highlight is Inland Auto Registration Service. The business helps customers with vehicle registration services as a California DMV partner, providing a local option for those looking to take care of their vehicle registration needs. By offering registration assistance in the community, Inland Auto Registration Service helps make essential vehicle-related services more accessible to local residents.


Contact:

(909) 676-1344


Location:

931 W. Holt Blvd., Suite B

Ontario, CA 91762

The West Valley Business Connector Program is designed to encourage the community to shop local during project construction. Participation is free for eligible businesses along the project route in the Cities of Ontario, Pomona, Montclair, and Rancho Cucamonga.


Participating businesses will be: 


  • Highlighted on @goSBCTA's social media platforms (Facebook and Instagram)
  • Shared in bi-weekly project construction alerts
  • Featured on the project webpage via Google Maps


To learn more and sign up, visit goSBCTA.com/WestValleyConnector.

ABOUT THE PROJECT

The West Valley Connector (WVC) project will be a 100% zero-emission Bus Rapid Transit (BRT) system, the first stage of the San Bernardino County zero-emission Bus Initiative and second BRT route in San Bernardino County.


Phase I of the project is 19 miles and will upgrade a portion of existing Route 61 which runs along Holt Boulevard, adding approximately 3.5 miles as center-running, dedicated bus-only lanes. There will be 21 stations in Phase I that will provide an improved transit connection to Ontario International Airport (ONT) and help build transit connectivity by linking ONT, two Metrolink lines (San Bernardino and Riverside) and multiple major activity centers along the route including Ontario Mills and Victoria Gardens. Headways will be 10 minutes in the peak commute period and 15 minutes off-peak, providing a high level of service to the community.

 