Dear Members
Update for Day 9, June 2nd work of the Single Family HOA Roadway Repaving Project. As previously mentioned, the schedule for repaving is dependent on the weather.
The Contractor has completed all of Barclay Lane and the roadway is fully open. On Friday the contractor completed the first course on most of Amberwood. Please note that you can drive on this initial course. Completion of the roadway with the final course will start on Monday, June 5th and should be done by the end of the day. Please note: As they start the final paving, they will spraying tacking material on the lane they are working. Do not drive on that as it will tack into the driveways. Once completed on Monday, please do not drive on it for about 24 hours.
After Amberwood, they will move on to either Rolling Oaks or Marble Court. We will be talking to the contractor on Monday morning to get a better idea of their schedule which is dependent on the weather and asphalt trucks they call to deliver the material. We will let everyone know of the schedule based on the work on Monday.
Remember, during the paving operation, roadway access will be limited to local residents only. Remember, once the final paving is installed on that roadway, please don’t travel on the roadway for about 24 hours or have any vehicles parked on the roadway as the tires might leave indentations. If you must drive on the roadway, please be careful. For example, do not turn your front wheels of the car while stopped on the pavement as that will leave a mark.
As we mentioned previously, due to the heavy weight of the garbage trucks, we will be talking to Collier County waste management on Monday to determine schedules for their trucks on Tuesday, June 6th.
We will keep you informed of the progress and schedule.
Thank you,
The Strand Single Family HOA Board of Directors
|