NOVEMBER 23, 2021 SPECIAL BOARD OF EDUCATION MEETING
The Francis Howell Board of Education met in special session tonight in the Board Room of the Administration Building. Open session was livestreamed via the District's YouTube channel and you can view the recording by visiting FHSD on YouTube. The full agenda and supporting documents are available on BoardDocs.
Prop S Construction Update
Revised cost projections for the Francis Howell North project were presented to the Board by SM Wilson, the District's construction manager. Due to an unprecedented increase in material and labor costs, construction of the new Francis Howell North project will require $164.7M. This is considerably higher than the original project budget of $83.5M estimated in 2018 as part of the Prop S planning. The Board and Administration, with input from the Facilities Committee and members of the community, must now consider the ramifications of this revised cost projection and determine how to move forward in the most fiscally responsible way.

The Board will hold a special work session at 6:30 p.m. on Tuesday, Dec. 7 to consider options for the Francis Howell North project and ask additional questions of Administration and SM Wilson.

The Board invites FHSD staff, students and residents to come together as we grapple with this unfortunate news and determine how to move forward with North and the additional Prop S projects that may be impacted.

Special Board meetings and work sessions do not typically include patron comments, but given the magnitude of this decision, the Board will designate a 30-minute period for patron comments during the Dec. 7 meeting; patron comments must be related to Prop S and the Francis Howell North construction project. Additionally, patrons are encouraged to email Board members with questions, concerns and comments prior to the work session so that all voices can be heard.

No votes or Board action regarding the Francis Howell North project will take place until the regularly scheduled Board meeting on Dec. 16.
SM Wilson's full presentation is available on BoardDocs. Highlights from the presentation include:

  • Market Conditions - Material costs across the construction industry are at an all-time high. On average, materials are up 30% in the last 12 months, and certain materials have increased in price by as much as 400%. Transportation and freight costs are up more than 200%. Supply chain volatility has created labor and schedule inefficiencies, and construction is in high demand after COVID-related slowdowns in 2020, which is further driving up prices.

  • CMAR Process - The Construction Manager At Risk, or CMAR, process has provided benefits to the District. The timing of early bid packages has accelerated project timelines, allowing steel and other materials to be delivered much earlier and for a lower price than would be possible with a traditional process.

  • Market Predictions - There is no guarantee that prices will come down. Industry experts believe that inflation escalation will continue through at least 2023 and that prices will not return to pre-2021 levels. Construction demand is expected to continue to increase.

  • Market Protection for FHSD - Using the CMAR process, the District was able to lock in pricing for early bid packages (earthwork, site utilities, building concrete, precast concrete, structural steel, underground plumbing and electrical rough-in). The final bid package - which includes the balance of the building, stadium, balance of the fields and sitework, and demolition of the current FHN - will be protected from future price escalation once the Board approves the Guaranteed Maximum Price, or GMP.
GRAPH: This graph courtesy of SM Wilson shows the escalation in the Building Cost Index (the average cost of building) from the time the original Prop S budgets were established in 2018 to today.
Next Board of Education special work session: Tuesday, December 7, 2021
Next regularly scheduled Board meeting: Thursday, December 16, 2021