Bid validity period is a real challenge with quickly changing prices. Trade contractor supplier pricing is good for only 7 to 14 days due to supply chain.
Shortages and tight supply along with frequent price increases is seemingly happening across all aspects of building and infrastructure construction.
Here is what we heard at our roundtable as to some of the reasons behind supply delivery and price volatility challenges.
- Texas is a world leader for petrochemical manufacturing supplying to other industrial manufacturers including automotive and construction. The winter storm early in 2021 has had a devastating impact on production because of emergency shut-downs and damage from burst pipes, damaged equipment necessitating several plants to be rebuilt from scratch. PVC products, additives, firestopping affected. Expect to see paint shortages shortly.
-
World-wide shortage of shipping containers.
-
Port congestion is delaying unloading and delivery of materials
-
Government stimulus programs in Asia are driving heightened demand for construction materials thus keeping materials in those regions.
-
Drywall - North American market is sold out. Suppliers are on allocation. There have been 3 or 4 instances in Eastern Canada where the distribution network had no inventory of 5/8" drywall to sell to suppliers.
-
Lumber is very limited. Suppliers buying blind as to price. When supply arrives in 6 to 12 weeks the price is when lumber is delivered. Plywood costs doubled - $100 a sheet. OSB 7/16" is now more expensive than plywood.
-
Steel - At beginnng of Covid the steel industry closed or reduced capacity significantly from around 87% utilization to less than 50%. Capacity is slowly increasing in North America. Canam Steel is a major buyer and used to be able to buy 6 months in advance and now being limited to less than 30 days. Pricing has doubled from November 2020 from $600-$700 per metric tonne to $1,300-$1,400 per metric tonne. Used to be able to guarantee quotes upwards to 2 to 3 months - now 15 days. Steel mills advising that they won't see stability until Q1 or Q2 2022. Interesting to note that the large distribution centres for AMAZON, KMart, etc is forecast to consume 65% of steel produced in North America in next 24 months with a construction program estimated at $100 Billion.