Weekly Engineering Update
Citywide Bus Stop Improvement Project – Notice of Construction
The City will be upgrading and improving the bus stops within the City at both City maintained stops and SamTrans maintained stops. In 2019, the City received $1 Million to improve the bus stops from the Affordable Housing and Sustainable Communities (AHSC) grant as part of the Light Tree housing project. These improvements will include new bus shelters, trash cans, concrete improvements, and other amenities. Construction is scheduled to begin 5/20/2024. For details on the schedule and location of work, please visit the project page: https://www.cityofepa.org/publicworks/project/city-wide-bus-stop-improvement-project
Encroachment Permits Issued and Underway
o Permit PW2023-0067 – East Palo Alto Sanitary District sanitary replacement project is currently underway. The work is on Beech Street from the easterly end to Clarke Avenue, Clarke Avenue from Beech Street to Green Street, and Green Street from Clarke Avenue to Cooley Avenue (near completion by end of May or mid-June 2024). Additionally, EPASD completed work on O’Connor Street and the roadway repairs will take place June/July 2024.
o Permit PW2024-0043 located at 903 Beech St. Work to be completed by 08/05/2024 by Comcast.
o Permit PW2024-0049 located at 1982 West Bayshore Road. A waste storage bin will be stored in front of the above property address for pick up by Recology.
o Permit PW2024-0058 located at 2100 University Avenue. Tree pruning work is to be completed by FMA Landscaping Services and is estimated to be completed by 7/20/2024.
o Permit PW2024-0053 located at intersection of Tulane Ave and Georgetown St to be completed by 09/04/2024.
o Permit PW2024-0060 located at the intersection of Woodland and University Ave to be completed by 10/10/2024 by Golden State.
o Permit PW2024-0057 located at 2100 University Ave to be completed by 10/06/24 by FMA Landscaping.
o Permit PW2024-0049 located at 1982 Bayshore Rd to be completed by 10/09/24 by Woodland Creek Homeowners.
o Permit PW2024-0065 located at 2290 University Ave to be completed by Bay Area Paving by 10/21/2024.
o Permit PW2024-0062 located at 2289 Lincoln St to be completed by Discount Plumbing by 10/20/2024.
AT&T:
o Permit PW2024-0050 located at 1637 Woodland Ave. to be completed by 09/11/2024: work consists of TCP pole.
o Permit PW2024-0051 located at 1781 Bayshore Rd. to be completed by 09/11/2024: work consists of fiber work.
The following permits from PG&E involve electrical work. There will be traffic control at these areas:
o Permit PW2023-0010 located at 2206 Clarke Ave. Work to be completed by 7/31/2024.
o Permit PW2024-0024 located at 67 various locations. Work to be completed by 06/12/2024 - (07/31/2024). Work consists of trimming trees.
o Permit PW2024-0034 located at 809 Schembri Lane. Work to be completed by 07/15/2024.
o Permit PW2024-0009 located at 1767 Woodland Ave. Work to be completed by 11/01/2024.
o Permit PW2024-0038 at various locations Woodland, Euclid and Bell. Work to be completed by 07/31/2024.
o Permit PW2024-0041 at 957 Myrtle St. Work to be completed by 07/31/2024.
o Permit PW2024-0044 at 1174 Westminster Ave. Work to be completed by 08/07/2024.
o PW2024-0020 on Addison Avenue and Oakwood Drive. Work to be completed by 08/30/2024.
o PW2024-0066 on 1614 Purdue Ave: work to be completed by 08/31/2024.
o PW2024-0018 on Bay Rd and Westminster Ave: work to be completed by 08/31/2024.
o PW2024-0069 on 952 Beech St: work to be completed by 07/30/2024.
o PW2024-0033 on 2208 Menalto Ave: to be completed by 07/02/2024.
o PW2024-0046 on 1950 Bay Rd: to be completed by 08/22/2024.
o PW2024-0035 on 342 Wisteria Dr: to be completed by 09/09/24.
o PW2024-0054 on 2249 Capitol Ave to be completed by 09/09/24.
o PW2024-0055 on 895 Schembri Ln. to be completed by 09/11/24.
o PW2024-0056 on 1686 Michigan Ave. to be completed by 09/15/24.
o PW2023-0069 at 952 Beech St to be completed by 08/15/2024.
|