West Avenue Phase 2 Project Advisory

Daytime Watermain Work Scheduled for Jan. 9, 2025

Temporary water service shutdown expected on1600 Block of West Ave.

 

What’s New 

Watermain and the outfall pipe installation continues from the pump station site within the city-owned P-24 parking lot at 1671 West Avenue (next to the U.S. Post Office) to the green space on the northwest corner of West Avenue and 17 Street.

 

On Thursday, January 9 between 10 a.m. and 4 p.m., the contractor will connect two new water service lines and relocate a section of watermain along West Avenue from just north of Lincoln Road to 17 Street. This will require a temporary water shutdown to 1688 West Avenue and 1666 West Avenue, only during the operation. This operation is scheduled between 10 a.m. to 4 p.m. to avoid nighttime disruptions. The project team has already advised both of these properties directly of forthcoming work.

 

West Avenue will remain closed in both directions in front of the pump station site. Drivers and bicyclists will continue to be directed to use Alton Road.

 

Additional updates will be distributed to provide notice on the remaining parts of work and any associated lane closures. Please carefully follow all posted signage and directions to speed limits, lane closures and detours.


Project Overview and Benefits

The project’s critical upgrades represent a comprehensive neighborhood improvement program, focused on resolving challenges associated with climate impacts and aging infrastructure. The proposed improvements within the West Avenue neighborhood include replacement of the existing water distribution/transmission systems and gravity sanitary sewers; installation of a robust storm water drainage collection and pumping system, including the raising of the paved roads, sidewalks and harmonization within the adjacent private properties; installation of street and pedestrian lighting; installation of new traffic signals and mast arms; installation of landscaping and irrigation; and construction of a segment of new Baywalk.


Segment 1 Pump Station Work

The P-24 parking lot will remain fenced and closed as work continues. All construction associated with the pump station is anticipated to last approximately two years. Please note, this schedule may change due to weather or unforeseen circumstances.

Next Steps

The underground utility and roadway work within the West Avenue neighborhood is being scheduled. A pre-construction public meeting will be conducted prior to the start of neighborhood work for Segments 2 through 9. 


Thank you for your continued patience and cooperation throughout the West Avenue Phase 2 Neighborhood Improvement Project. 


Contact

Should you have any questions regarding this project, please contact:

Heather M. Leslie, Public Information Liaison

Call/text 305.905.5876 or email: heather@hmlpublicoutreach.com

To learn more about the city’s innovative initiatives, visit www.mbrisingabove.com


To request this material in alternate format, sign language interpreter (5-day notice required), information on access for persons with disabilities, and/or any accommodation to review any document or participate in any city-sponsored proceedings, call 305.604.2ADA (2232) (voice), select 1 (English) or 2 (Spanish) and leave a message with your request. TTY users may call via 711 (Florida Relay Service). You can also make requests online at www.miamibeachfl.gov/ada by selecting ADA request.

Facebook  Twitter  Instagram