Drop Construction Progress
As of the writing of this newsletter, there are 10 fully completed drops that will be contacted towards the end of next week to set up an installation time. Those homes will be contacted via email, text message or voice call to schedule an appointment. Those who are currently under construction for a drop will be ready for an indoor installation once the construction is completed and light to the home is verified.
As it stands right now, there are 68 requests for service on Colorado and Gunderson Rd. The remaining 58 requests will begin sequential construction on the week of March 18th. Given the clustering of orders, crews will most likely be working west on Colorado towards 362nd. Two crews will be performing drops. Clackamas County will be constructing the aerial drops using their in-house crews and, FiberTel will be building out the underground home drops. FiberTel is set to start in late March or early April, so it will be a few more weeks before those with underground drops are notified. The speed in which aerial drops can be construction is not entirely known at this point but will be identified in the upcoming weeks, once aerial construction begins. Once the buildout speed is identified, SandyNet and CBX staff members will be able to better guess how long the remaining drop construction will take to finalize.
Feel free to reach out and verify your order status with SandyNet staff. While we won’t be able to provide a firm construction date until earlier next month, we can make sure your order is confirmed and on the schedule to be built out.
|