Crews have restriped lanes and placed temporary concrete barriers along westbound Katella Avenue as they prepare to construct a new bike lane between Epson Way and the freeway. Upcoming work will include demolishing the sidewalk and relocating utilities.
The outside lane on westbound Katella between Epson Way and the northbound I-605 on-ramp is closed to create a work zone for crews.
Beginning early September, crews are expected to close the outside lane on eastbound Katella to begin preliminary activities as they prepare to construct a bike lane on this side of the street.
Work hours are 6 a.m. to 4 p.m. daily with intermittent night work from 9 p.m. to 5 a.m. for certain activities.
Sidewalk Access
Sidewalk access on westbound Katella is closed. Signs are in place detouring pedestrians and bicyclists to use the sidewalk on eastbound Katella, which will be maintained throughout construction.
Retaining Wall Work on Westbound Katella
Crews are expected to begin work on the first of three retaining walls to be constructed to accommodate project improvements. This retaining wall will be built along westbound Katella Avenue within the Coyote Creek Channel.
Center Median Reconstruction Complete
Reconstruction of the center median on Katella Avenue beneath I-605 freeway that began in July was recently completed, and features a raised brick style island median.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
|