Northbound McFadden Avenue On-Ramp

Extended Closure

WHAT:

Crews are expected to reconstruct the northbound SR-55 McFadden Avenue on-ramp, which will require an extended closure of the ramp.


Visit www.octa.net/55Construction to view updates regarding construction activities and closures.


WHEN:

The on-ramp is expected to close as soon as 9 p.m., Tuesday, April 7 and reopen to motorists by 5 a.m., Friday, April 17.


This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Railroad Bridge Girder Installation Complete!

Last week, crews successfully installed precast girders on the east side of the bridge over the railroad. This activity required tremendous effort and coordination between contractors, construction management teams, Caltrans, Metrolink, and other external subcontractors. We thank and appreciate the public for allowing crews to complete the work safely.

Activities and Closures Coming Soon!

Railroad Bridge Falsework Removal

In mid-April, crews are expected to remove falsework along the east side of the SR-55 bridge over the railroad, which will require nighttime lane and ramp closures. Additional information will be provided in future communications.

Southbound Dyer Road Off-Ramp Extended Closure

In late-April, crews are expected to reconstruct the southbound Dyer Road straight off-ramp, which will require an extended closure of the ramp. Additional information will be provided in future communications.

Closures and Detours Map

Bookmark the closures and detours map for quick access to real-time construction information. Click on the construction icons to view activities and closures.

About the Project

OCTA, in cooperation with Caltrans, is improving 4 miles of SR-55 between I-405 and I-5. The project will improve traffic flow and reduce travel time by adding one regular lane and one carpool lane in each direction. Also, the project will add merge lanes between several interchanges and stripe carpool lanes for continuous access, augmenting safety on the freeway by making merging easier. These enhancements are expected to create a better, smoother driving experience for motorists.

 
Stay Connected-01.png
Facebook  Instagram  X

octa.net/SR55South

888-371-2555

SR55Info@octa.net

@55FWYProject