OCTA Logo and I-5 Improvement Project Logo on top of a faint image of the I-5 Freeway.

As of July 31, 2026

有關此項目的更多信息,請聯繫 I-5 社區服务團隊,郵箱為 i5Project405to55@octa.net 或電話 888-209-5555,或查看 octa.net/i-5project.

 

이 프로젝트에 대한 자세한 내용은 I-5 Community Outreach Team에 이메일(i5Project405to55@octa.net) 또는 전화(888-209-5550)로 문의하시거나, octa.net/i-5project를방문해주시기바랍니다.

Click on this image to view construction activities on the project interactive map.
Image is of a clipboard with a traffic cone on it to encourage people to click on the link next to it to view a detailed closure list

To view and print a detailed list of closures and detours, CLICK HERE!

Segment 2 (Yale Avenue to SR-55)

Project Activities

ONGOING WORK

 

BRIDGE DEMOLITION AT EL MODENA TUSTIN CHANNEL/I-5 BRIDGE

Daytime construction activities are expected to start for the demolition of the outer portions of I-5 at El Modena Tustin Channel bridge.


For more information on I-5 mainline lane and ramp closures and associated detours, please click on the Google Map.


Anticipated Schedule

Monday, Aug. 3 through Friday, Aug. 7.


Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 9 p.m. to 5 a.m.



BRIDGE DEMOLITION & CIDH ACTIVITIES AT PETERS CANYON HIKING & RIDING TRAIL/I-5 BRIDGE

Picture depicts Peters Canyon Trail Closures

Nighttime construction activities and closures are resuming for the demolition of the remaining outer portions of I-5 at the Peter Canyon Hiking & Riding Trail. This work requires full closures of westbound (WB) and eastbound (EB) Peters Canyon Trail between Bryan Avenue and Harvard Avenue/Walnut Avenue.



Daytime construction activities are ongoing at the I-5 Peters Canyon Hiking and Riding Trail Bridge for cast-in-drilled-hole (CIDH) work.


Intermittent full closures of the Peters Canyon Hiking and Riding Trail at I-5 may occur through late 2026 for moving equipment in the construction area.


At least one lane in each direction will remain open at all times, unless otherwise noted.


Anticipated Schedule

Demolition: Monday, Aug. 10 through Friday, Aug. 14.

CIDH: Ongoing through late 2026.


Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 9 p.m. to 5 a.m.

BRIDGE DEMOLITION AND FULL ROAD CLOSURES AT JAMBOREE ROAD/I-5 BRIDGE

Nighttime construction activities and closures continue for the demolition of the outer portions of I-5 at Jamboree Road. This work requires intermittent full road closures of westbound (WB) Jamboree. Please note that crews may switch between EB and WB directions of Jamboree intermittently to conduct the work and implement closures.


Anticipated Schedule

Ongoing through Friday night, July 31.


Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 10 p.m. to 5 a.m.


 

PILE DRIVING/CIDH ACTIVITIES AT CULVER DRIVE/I-5 BRIDGE

Construction activities continue at the Culver/I-5 bridge, including pile driving to widen structures as a part of project improvements. Intermittent nighttime full closures and daytime lane closures on eastbound (EB) and westbound (WB) Culver Drive at I-5 may occur during the pile driving activity, to support I-5 widening work.


24/7 Long-Term Closure: Crews will install concrete barriers and close inside lanes on Culver at the I-5 bridge in both directions for a 24/7 long-term closure to conduct CIDH activities, to be scheduled this fall. Check back for the 24/7 long-term closure date.


Once implemented, the long-term closure will remain in place until mid-2027. At least one lane in each direction will remain open at all times, unless otherwise noted.  

 

Please note: To account for nighttime noise impacts, pile driving and CIDH activities are scheduled during daytime hours. Pile driving activities may be loud at times.


Anticipated Schedule

Pile Driving: Ongoing through mid-August 2026.

CIDH: fall 2026.

 

Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 10 p.m. to 5 a.m.

RETAINING WALL AND SOUND WALL CONSTRUCTION

Retaining wall (RW) and sound wall (SW) construction activities are ongoing and expected to continue along northbound (NB) and southbound (SB) I-5.


Anticipated Schedule

  • RW along SB I-5 between Culver and Georgia: Ongoing through late 2026
  • SW along NB I-5 Culver and Yale: Ongoing through Spring 2027
  • RW and SW along SB I-5 between Butterfly and Culver: Ongoing through late 2026
  • RW along SB I-5 between Tustin Ranch and Jamboree: Ongoing through late 2026
  • RW along NB I-5 near Culver on-ramp: Late August through Spring 2027
  • RW along SB I-5 near SR-261: Early August through September 2026
  • RW and SW along NB I-5 Culver on- and off-ramps: Mid-August through October 2026
  • SW and RW along NB I-5 near Red Hill: September 2026 through early 2027
  • RW along NB I-5 near Newport: Fall 2026 through early 2027


Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 10 p.m. to 5 a.m.


Closures

Daytime work is anticipated to occur behind concrete barriers while nighttime work requires freeway lane closures and intermittent closures of NB and SB I-5 Culver on- and off-ramps.


TRAFFIC SHIFTS ON RAMPS AND ROADWAY

Crews continue shifting traffic toward the center of I-5 as well as on the Tustin Ranch Road, Jamboree Road and Culver Drive on-and off-ramps.


Anticipated Schedule

Ongoing through early August.


Once shifted, traffic will remain on the temporary paved ramps through spring 2027, before being switched to the permanent newly reconstructed ramps.


Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 10 p.m. to 5 a.m.

 

OTHER ACTIVITIES


Crews continue with general highway construction including concrete barrier (K-rail) activities, equipment transport, and concrete pours, on and along NB and SB I-5 and bridge work on surface streets. Nighttime full ramp closures and street and freeway lane closures are necessary starting as early as 10 p.m. Friday, July 31 and continuing intermittently until 7 a.m. on Saturday, Aug. 8.


Neighboring Project


City of Irvine Long-Term Closure


Please note: Ongoing through October, the City of Irvine and Irvine Ranch Water District (IRWD) will continue water relocation activities on Culver near the I-5 bridge. This work requires WB Culver under the bridge to be reduced to one lane. Work and lane closures are expected Monday through Friday, from 9 a.m. to 3 p.m. Please contact the City of Irvine or IRWD for more information.

*This work may be loud and ongoing. The schedule is subject to change due to inclement weather or unforeseen operational issues.


*Freeway and street lane closures will occur regularly throughout the duration of the project's construction. At least one lane will be open to traffic at all times, unless otherwise specified. See closure section above for more information.

 

Segment 1 (I-405 to Yale Avenue)

Project Activities

ONGOING WORK

RETAINING AND SOUND WALL CONSTRUCTION

Retaining wall (RW) and sound wall (SW) construction activities, including demolition of existing walls followed by foundation and general wall construction, are ongoing and expected to continue along northbound (NB) and southbound (SB) I-5.


Anticipated Schedule

  • RW along SB I-5/Progress near Sand Canyon Avenue: Ongoing through fall 2026
  • RW and SW along NB I-5 near SR-133: Early August through early 2027
  • RW along SB I-5 near SR-133: Early August


Anticipated Work Hours

Daytime: As early as 7 a.m. to 4 p.m.

Nighttime: As early as 10 p.m. to 5 a.m.


Closures

Daytime work is anticipated to occur behind concrete barriers while nighttime work, as needed, requires freeway lane closures and intermittent closures of NB and SB I-5 and related on-and-off-ramps.


OTHER ACTIVITIES

Crews continue with vegetation removal, electrical work, concrete barrier (K-rail) activities and general preliminary highway activities on NB and SB I-5 as well as on NB and SB SR-133. Nighttime full ramp and connector closures, and street and freeway lane closures will be necessary as early as 9 p.m. Friday, July 31 and continuing intermittently until 5 a.m. on Saturday, Aug. 8.


Anticipated Work Hours

Daytime: As early as 7 a.m. to 4 p.m.

Nighttime: As early as 9 p.m. to 5 a.m.


Neighboring Project


City of Irvine Ongoing Nighttime Closures


Please note: The City of Irvine continues to carry out underground utility activities. Nighttime closures of the median and inside lanes along Sand Canyon Avenue at I-5 are necessary Friday, July 31 through Thursday, Aug. 6, between 9 p.m. and 4 a.m. Please contact the City of Irvine for more information.

*This work may be loud and ongoing. The schedule is subject to change due to inclement weather or unforeseen operational issues.


*Freeway and street lane closures will occur regularly throughout the duration of the project's construction. At least one lane will be open to traffic at all times, unless otherwise specified. See closure section above for more information.

 

Google Map

A clickable preview of the I-5 Improvement Project area on Google Maps. Click this image to view the interactive map on Google Maps.

Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.

""

Stay Connected

 

We invite you to sign up for project updates so you’ll be the first to know about upcoming construction activities, traffic changes, and community meetings and when we’ll be out in your community at local events - we hope you’ll stop by and say hello!



This screenshot outlines the I-5 Improvement website where constituents can sign up to receive Project Updates.
 

About the Project

Project Map

A horizontal map of the I-5 Improvement Project in Irvine and Tustin. Click the map to view it as a PDF.

Click to view a larger map

Click to view vertical map on a mobile device

A chart displays the Construction Schedule. Segment 1 is anticipated to be complete in late 2029. Segment 2 is anticipated to be complete in mid-2030. The schedule is subject to change.

For more information, view the Project Website and Fact Sheet:

" "
 
An illustration reads "Follow us on socials!" next to a cell phone on top of an orange background.

STAY CONNECTED