Dear Members,
Update for Day 7 evening, May 31st, of the Single Family HOA Roadway Repaving Project. As previously mentioned, the schedule for repaving is dependent on the weather as we saw today.
The Contractor has completed the first stage of paving on Barclay Lane. Depending on the weather tomorrow morning, they will finish Barclay and move on to Amberwood later in the morning. Due to the size of the Amberwood roadway, completion for Amberwood will probably take all day Thursday and part of Friday, June 2nd.
Remember, during the paving operation, roadway access will be limited to local residents only. Remember, once the final paving is installed on that roadway, please don’t travel on the roadway for about 24 hours or have any vehicles parked on the roadway as the tires might leave indentations. If you must drive on the roadway, please be careful. For example, do not turn your front wheels of the car while stopped on the pavement as that will leave a mark.
As we mentioned previously, due to the heavy weight of the garbage trucks, they will not be on our streets this Friday, June 2, but will be back next Tuesday, June 6th for normal pickups.
We will keep you updated on the progress and schedule with an email tomorrow.
Thank you,
The Strand Single Family HOA Board of Directors
|