Center Infrastructure Improvement Project Newsletter

Project Updates

Please be advised that northbound travel lanes will be closed on Thursday, May 15th to accommodate sanitary sewer repairs being performed by Paramount for the MDC. This work is being closely coordinated and needs to be performed before the roadway project advanced to other areas of LaSalle Road. Private duty police will be on-site to manage traffic control and assist with pedestrian crossings to ensure everyone’s safety. This critical utility work is being coordinated with Gerber and must take place prior to the installation of new curbing and sidewalks.


In addition to the sewer repairs, crews have recently installed soil cells and trenching work is also underway. We appreciate the patience and cooperation as we continue these important infrastructure improvements in the Center!

Two-Week Project Look-Ahead

Stay informed about upcoming construction activities in West Hartford Center. Here's what to expect in the next two weeks:


May 14

  • Crew #1 completes grading and backfill of conduit and resumes curb excavation in Phase 1-A
  • Crew #2 completes grading and backfill for conduit in Phase 1-B

May 15

  • Crew #1 continues excavation for curb and supports curb installation
  • Crew #2 installs soil cells and light pole foundations in Phase 1-B

May 16

  • Crew #1 excavates for curb in Phase 1-B, backfills curb, and grades walkways as needed
  • Crew #2 completes soil cell work and trenches for conduit in Phase 1-B

May 19-23

  • Install storm drainage along LaSalle Road
  • Backfill curb and grade sidewalks throughout the work zones
  • Form and pour sidewalks
 

In the News

West Hartford Community Interactive (WHCi) recently toured the West Hartford Center construction site to give a closer look at the ongoing improvements. The video highlights current progress, explains key elements of the work, and offers a preview of what’s to come.

Thank You to Local Businesses

If you need additional printouts of project materials or have any questions, please don't hesitate to reach out to us at CenterConstruction@westhartfordct.gov. We're here to help!

Get the Business Toolkit

Resources to Help Your Business Navigate the Construction Period

 
 
 

We recognize that construction projects can present challenges for local businesses, and we're here to support you. To assist you during this time, we've developed a resource library filled with helpful tips and materials designed to keep you and your employees informed and prepared.

 

Parking Information for Employees During Construction

As construction progresses, we're working to maximize on-street parking for customers and visitors. To help, we encourage employees to use alternative parking options, including the Town Center Parking Garage, which offers reduced rates for retail and restaurant employees working in the Center.


The Town Center Garage rates are far lower than other options! The rates are $4.50 for up to an 8.5-hour shift and $7 for anything over 8.5 hours.


For more info, contact Kristen Gorski, Economic Development Coordinator, at kristen.gorski@westhartfordct.gov.

 

Stay Informed and Ahead of the Curve

For the latest updates and important information about the project, visit our project webpage. It’s your go-to resource for all the news, timelines, and tools to help your business navigate the construction period smoothly.

 

Have questions or feedback? We’re here to help—email us at CenterConstruction@westhartfordct.gov