Dear Inverness Residents,
July 27 - Prime Coat
Weather permitting, on Monday July 27, Geske and Sons Paving will begin applying a Prime Coat (FRESH OIL) in the neighborhood north of Baldwin Road and will work southward through the Village. The operation is expected to take up to ten (10) days to complete, depending on weather conditions and construction progress.
Please note, when first applied the asphalt prime coat is very sticky and difficult to remove from shoes, clothing and vehicles. Walking or driving on the prime coat immediately after application is not recommended.
The material may also leave marks on your driveway if you drive through it before it has cured. The prime coat can be very difficult to remove if it splashes onto your vehicle. Please avoid driving on the prime coat whenever possible. If driving on the material cannot be avoided, proceed very slowly (approximately 5mph) to minimize splattering. If the material gets on your vehicle, automotive tar remover or WD-40 and a soft cloth can be used to help remove it.
If you must leave during, or shortly after the prime coat application, you may wish to delay your return for one (1) to two (2) hours to allow the material to cure. For concrete and paver driveways, we recommend not pulling back into your driveway for at least one (1) to two (2) hours following application. The prime coat typically cures within a few hours, at which point tracking is substantially reduced, although not completely eliminated.
For asphalt aprons and driveways, some tracking of the material may occur. You may wish to avoid driving on these surfaces until the material has fully cured.
July 27 - Start of Paving Operations
Weather permitting, at 7:00 a.m. on Monday, July 27, Geske and Sons Paving will begin placing the initial asphalt binder layer.
Work will begin in the Old McIntosh neighborhood north of Baldwin Road. The asphalt will be placed in two (2) lifts, with the final asphalt lift scheduled for later in the week, weather permitting. No additional notice will be issued, as this notice serves as notification for paving operations throughout the week of July 27 - potentially into the following week.
Driveway access may be temporarily interrupted during paving operations. Please follow the directions of flagging crews and construction personnel at all times. Roads and driveways will be fully accessible once paving operations are complete.
If adverse weather conditions prevent the prime coat application or paving operations from taking place as scheduled, the work will be postponed to the following day.
If you have any questions regarding the road program, please contact Village Hall at (847) 358-7740 or contact@inverness-il.gov.
Regards,
Jack Tatooles,
Mayor
|