Construction continued in September on Phase II of the State Route 60/Potrero Boulevard Interchange Project. See the latest improvements taking shape across the project area in this month’s Potrero in Progress video below.

 

POTRERO IN PROGRESS – SEPTEMBER 2026

SEPTEMBER 2026 CONSTRUCTION HIGHLIGHTS

Here’s a quick recap of the progress crews made across the project:


  • Earthwork and grading continued throughout the project area, helping prepare the site for future roadway and interchange improvements.


  • Drainage and sewer improvements progressed in several areas, including continued installation and testing of underground infrastructure.


  • Crews advanced retaining wall and embankment construction to support future on- and off-ramp construction.



  • Traffic-control and erosion-control improvements continued to help maintain a safe work zone and prepare the site for changing weather conditions.

FOLLOW THE PROGRESS

Looking to see more updates on the State Route 60/Potrero Boulevard Interchange Project?


Follow @PotreroIC on social media for construction updates, upcoming work, and project milestones.

undefined

ABOUT THE PROJECT

The Riverside County Transportation Commission (RCTC) and the City of Beaumont, in partnership with Caltrans, are constructing “Phase II” of the State Route 60/Potrero Boulevard Interchange Project. This phase will deliver major roadway and interchange improvements to improve traffic flow and access to and from SR-60, strengthening connections and regional mobility in Beaumont and across western Riverside County. 

 

Phase II includes the construction of a six-ramp partial cloverleaf interchange, the realignment of Western Knolls Avenue, and the widening of Potrero Boulevard to six lanes.