Dear Members
Update for Day 10, June 5th work of the Single Family HOA Roadway Repaving Project. As previously mentioned, the schedule for repaving is dependent on the weather.
The Contractor has started the FINAL paving course on Amberwood and should be done by the end of the day. Please note: As they start the final paving, they will spraying tacking material on the lane they are working. Do not drive on that as it will tack into the driveways. Once Amberwood is completed, please do not drive on the new pavement for about 24 hours. There should be no contractor deliveries (large trucks) on Tuesday. Amberwood will be completely open on Wednesday assuming the weather doesn’t stop the work today.
If you must drive on the roadway, please be careful. For example, do not turn your front wheels of your car while stopped on the pavement as that will leave a mark.
As we mentioned previously, due to the heavy weight of the garbage trucks, we will be talking to Collier County waste management today to determine schedules for their trucks on Tuesday, June 6th for Amberwood.
Whisperwood, Rolling Pines and Barclay will have normal garbage and recycle pickups on Tuesday, June 6th. We will update everyone later today.
Thank you,
The Strand Single Family HOA Board of Directors
|