AWIN Upgrade Update
As the statewide upgrade of the AWIN system continues, the current focus is on tower site refurbishment. All AWIN towers have been inspected to determine whether refurbishment will be required. So far, upgrading of the microwave equipment has been completed on 54 sites (over half the total) that did not need significant tower refurbishment first.
Engineering plans are ongoing for the more than 40 tower sites that remain. Engineers have been sorting them into eight groups which can go through the next phases of development. The first two, Groups A and B, have been through the bidding and contracting phases. Work will begin on these groups next week. A bidder has been selected for Group C and the contract details are now being finalized. Group D will go out for bid next month. The remainder will be staggered in the months ahead.
No significant outages are anticipated during the construction work of a tower refurbishment. There is the possibility the site will need to be taken down temporarily when equipment is being removed or added, but duration will likely be minimal. AWIN Alerts will be sent out in advance of planned outages. As always, AWIN highly recommends that all AWIN Users have a plan for backup communications.
Visit the AWIN web page to sign up for AWIN Alerts. Please be aware: At the time of this newsletter release, we are experiencing a temporary disruption to the website, which should be resolved shortly. Keep checking back.
|