As of Nov. 20, 2026

有關此項目的更多信息,請聯繫 I-5 社區服务團隊,郵箱為 i5Project405to55@octa.net 或電話 888-209-5550,或查看 octa.net/i-5project.

 

이 프로젝트에 대한 자세한 내용은 I-5 Community Outreach Team에 이메일(i5Project405to55@octa.net) 또는 전화(888-209-5550)로 문의하시거나, octa.net/i-5project를방문해주시기바랍니다.

Our Next Friday Alert will be sent on Dec. 4.

Click on this image to view construction activities on the project interactive map.

To view and print a detailed list of closures and detours, CLICK HERE!

Segment 1 (I-405 to Yale Avenue)

Project Activities

ONGOING WORK

TEMPORARY ASPHALT CONCRETE PAVING & TRAFFIC SHIFT

Nighttime construction activities are expected at the northbound (NB) I-5 Jeffrey Road off-ramp for the placement of temporary asphalt concrete. Traffic will be shifted onto the temporary pavement/off-ramp to allow for the demolition and reconstruction of the existing ramp.


Anticipated Schedule

Temporary Asphalt Concrete Placement: Monday, Dec. 7.

Traffic Shift Activity: Tuesday, Dec. 8.


Anticipated Work Hours

Daytime: As early as 7 a.m. to 4 p.m.

Nighttime: As early as 9 p.m. to 5 a.m.


Temporary striping and concrete barrier placement will also occur during this time. Once shifted, traffic will remain on the temporary paved road before being switched to the permanent, newly reconstructed ramps.


Nighttime freeway lane and ramp closures will occur intermittently. At least one lane in each direction will remain open at all times, unless otherwise noted.


For more information on associated closures, please view the Google Interactive Map, or plan your route using the Waze navigation app.

OTHER ACTIVITIES

Crews will continue general highway construction, including electrical work, striping, concrete barrier (k-rail) placement, and signage activities on the NB and southbound (SB) sides of I-5 and SB SR-133. Nighttime freeway lane closures, as well as full ramp and connector closures will be necessary as early as 9 p.m. Friday, Nov. 20 and continuing intermittently until 5 a.m. on Wednesday, Nov. 25.


For more information on these closures and associated detours, please view the Google Interactive Map, or plan your route using the Waze navigation app.


Anticipated Work Hours

Daytime: As early as 7 a.m. to 4 p.m.

Nighttime: As early as 9 p.m. to 5 a.m.

*This work may be loud and ongoing. The schedule is subject to change due to inclement weather or unforeseen operational issues.


*Freeway and street lane closures will occur regularly throughout the duration of the project's construction. At least one lane will be open to traffic at all times, unless otherwise specified. See closure section above for more information.

 

Segment 2 (Yale Avenue to SR-55)

Project Activities

ONGOING WORK

NOW OPEN! LONG-TERM LANE CLOSURES AT JAMBOREE ROAD/I-5 BRIDGE

LANES REOPEN! On Wednesday night, Nov. 18, crews completed restriping and the removal of the median concrete barriers allowing the lane closest to the median in each direction of Jamboree Road at the I-5 bridge to reopen, ahead of the Thanksgiving Holiday!


We thank you for your patience and understanding during construction!

BRIDGE CONSTRUCTION ACTIVITIES AT CULVER DRIVE/I-5 BRIDGE

Image shows available detour routes for Eastbound Culver Drive full closures
Image shows available detour routes for Westbound Culver Drive full closures

Construction activities are expected to take place at the Culver Drive/I-5 Bridge for bridge widening activities including cast-in-drilled-hole (CIDH). In order to carry out this work, long-term closures of the lane closest to the median in both directions of Culver will be necessary.


Anticipated Schedule

Long-Term Lane Closures Implementation: Week of Nov. 30 (weather permitting).

A nighttime full road closure is expected.

CIDH Work: Tentatively, winter 2027.

Nighttime full lane closures are expected.


For more information on these closures and associated detours, please view the detour maps above, the Google Interactive Map, or plan your route using the Waze navigation app.


Anticipated Work Hours

Daytime Work: As early as 7 a.m. to 4 p.m.

Nighttime Work: As early as 10 p.m. to 5 a.m.


Closures

24/7 Long-Term Lane Closures: Crews will place concrete barriers along the eastbound (EB) and westbound (WB) lane closest to the median and close them off in both directions of Culver at the I-5 bridge. At least one lane in each direction will be open to traffic at all times, unless otherwise specified. The lane closures are anticipated to remain in place through winter 2027 to support additional I-5 widening work.


Nighttime freeway lane and ramp closures as well as full street closures will occur intermittently. At least one lane in each direction will remain open at all times, unless otherwise noted.

BRIDGE WORK ACTIVITIES ALONG I-5

Daytime construction activities, and some nighttime activities, are ongoing behind k-rail (concrete barriers) at various bridge locations along I-5. Activities include abutment work, girder installation, removal of temporary support structures, concrete pours for new bridge deck areas, barrier wall work, and roadway reconstruction to widen bridge structures as a part of project improvements.


For more information on closures and associated detours, please view the Google Interactive Map, or plan your route using the Waze navigation app.


Anticipated Schedule


El Modena Tustin Channel/I-5 Bridge

  • Abutment Work: Ongoing through late December.
  • Girder Installation: Tentatively, mid-December.

(Nighttime activity with partial mainline and ramp closures.)


Peters Canyon Hiking and Riding Trail/I-5 Bridge

  • Bridge Foundation, Abutment and Wall Work: Ongoing through spring 2027.
  • Temporary Support Structures Installation/Girder Installation: Tentatively, late 2026 through winter 2027.

Nighttime activity with full road closures; check back for more details.


Jamboree/I-5 Bridge

  • Rebar Work: Ongoing through Week of Dec. 7.
  • New Deck Concrete Pours: Tuesday, Dec. 8 and Thursday, Dec. 10
  • Barrier Wall Work: Winter 2027.

One nighttime full road closure is expected in February; check back for more details.

  • Roadway Reconstruction: Early 2027 through September 2027.


SR-261/I-5 Bridge

  • New Deck Concrete Pours: Tuesday, Dec. 1 and Thursday, Dec. 3.
  • Temporary Support Structures Removal: Winter 2027.

Two nights of full road closures are expected in February; check back for more details.


Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 10 p.m. to 5 a.m.


Nighttime freeway lane and ramp closures will occur intermittently. At least one lane in each direction will remain open at all times, unless otherwise noted.

RETAINING WALL AND SOUND WALL CONSTRUCTION

Retaining wall (RW) and sound wall (SW) construction activities, including demolition, CIDH work, and wall construction, are ongoing and expected to continue along NB and SB I-5.


As part of this work, nighttime activities for dirt removal are expected along NB I-5 near the Culver Drive on-ramp starting mid-December for approximately two weeks.


For the latest wall locations and construction schedule information, please visit the Google Interactive Map.


Closures

Daytime work is anticipated to occur behind concrete barriers, while nighttime work will require intermittent NB and SB I-5 lane closures and closures of related on-and-off-ramps.


Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 9 p.m. to 5 a.m.

OTHER ACTIVITIES


Crews continue general highway construction activities on and along NB and SB I-5, including striping, concrete barrier (k-rail) placement and bridge work. Nighttime freeway lane closures as well as full road and ramp closures will be necessary as early as 10 p.m. Friday, Nov. 20 and continuing intermittently until 5 a.m. on Wednesday, Nov. 25.

 

*This work may be loud and ongoing. The schedule is subject to change due to inclement weather or unforeseen operational issues.


*Freeway and street lane closures will occur regularly throughout the duration of the project's construction. At least one lane will be open to traffic at all times, unless otherwise specified. See closure section above for more information.

 
 

Google Map

A clickable preview of the I-5 Improvement Project area on Google Maps. Click this image to view the interactive map on Google Maps.

View the latest closures and detours using our Google Interactive Map, or plan your route using the Waze navigation app. Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.

""

Stay Connected

 

We invite you to sign up for project updates so you’ll be the first to know about upcoming construction activities, traffic changes, and community meetings and when we’ll be out in your community at local events - we hope you’ll stop by and say hello!



This screenshot outlines the I-5 Improvement website where constituents can sign up to receive Project Updates.
 

About the Project

Project Map

A horizontal map of the I-5 Improvement Project in Irvine and Tustin. Click the map to view it as a PDF.

Click to view a larger map

Click to view vertical map on a mobile device

A chart displays the Construction Schedule. Segment 1 is anticipated to be complete in late 2029. Segment 2 is anticipated to be complete in mid-2030. The schedule is subject to change.

For more information, view the Project Website and Fact Sheet:

" "
 
An illustration reads "Follow us on socials!" next to a cell phone on top of an orange background.

STAY CONNECTED

Facebook    X    Instagram    Web

i5Project405to55@octa.net

(888) 209-5550

octa.net/I-5Project

 
A footer image displays OCTA, Caltrans, US Department of Transportation and Building CA logos in a horizontal row..