Upcoming Lane Closures

Along Eastbound I-10

Pictured: Concrete batch plants supply our crews with well-mixed and consistent concrete to use in our pavement operations. Along with improving efficiency for projects with large concrete needs, these batch plants also allow for the recycling of unused concrete, reducing waste!

Upcoming Activity



Starting Monday, July 29 through Friday, August 2, 2024 from 7 p.m. to 5 a.m., nightly single lane closures are scheduled along eastbound I-10. These closures will allow crews to safely perform drainage repairs along the project area. If traveling in this direction, please remember to keep a watchful eye for crews working near live traffic and equipment in use.


New Traffic Switch


As construction progresses along the I-10, an eastbound traffic switch will take place Sunday, August 4, 2024 to shift traffic into the outer lanes. More details to come.


Westbound Rest Area Closure Continues


From Monday, June 24 through Monday, August 5, 2024, motorists can expect a COMPLETE closure of the Westbound I-10 Cactus City Rest Area. This closure will ensure crews can safely and efficiently complete water and sewer line construction and reconstruct the rest area on-and off-ramps. Please remember to plan ahead when traveling through the project area and be sure to keep a watchful eye for crews and construction equipment.

Neighboring Projects

Interstate 10 - Blythe Pavement, Beautification & Safety Enhancements

Caltrans continues work on a $241 million pavement, beautification, and safety enhancements project on I-10, in and near Blythe. The project includes concrete pavement rehabilitation of 88 lane miles, on and off ramps, and shoulders. Upgrades of curb ramps, sidewalks and crosswalk safety enhancements and “push button posts” to ADA standards (Americans with Disabilities Act). Crews continue prep work on the I-10 Blythe Pavement, Beautification, and Safety Enhancements project. Learn more here.


Caltrans Projects

Want to learn about Caltrans projects throughout District 8 and the entire state? Visit our website to explore a full list of upcoming and ongoing agency projects.


Make sure to stay in the know and follow @i10DesertRehab on X (Twitter) and Facebook for the latest project information and construction updates!

Project Background

The I-10 Desert Rehab Project segment is a 13-mile stretch of the I-10 freeway near Coachella in Riverside County, between 1.8 miles east of the Dillon Road Interchange and 2 miles east of the Cactus City Rest Area. Construction will take place over the next 3.5 years and includes repaving I-10, updating lane striping, and the addition of an eastbound truck climbing lane. The Cactus City Rest Area will also be closed for 1-2 months during construction. 


In addition to repairing and restoring existing roadway pavement and adding an eastbound truck climbing lane, the I-10 Desert Rehab Project will install electric vehicle charging stations at the Cactus City Rest Area, replace and upgrade bridge railings, guardrail systems, and roadway signage, and improve roadway infrastructure including drainage and stormwater treatment systems.

Neighboring Projects
Click here for more information on the I-10 Tune Up Project
Click here for more information on the I-10 Blythe Pavement Rehabilitation Project