W. Rosemary Street Community Meeting Summary

 

October 3, 2025

 


Dear Neighbor,


Thanks to all who were able to join us for the Community Meeting on September 30. Your input is very valuable as we near the start of construction on this project.


When construction begins on October 20, Moffat Pipe crews will start by moving equipment to the first site, and setting up erosion control measures in the first construction area. Maps of each construction area (1 through 8) will soon be available on the project webpage. On October 17, you will receive a project notice via email about the construction plans for the first week of the project.


Below you will find a summary of the September 30 meeting, plus information requested by those in attendance. If you have any questions about the meeting, please reach out to me, or one of the contacts below.


Sincerely,


Darren Berger

Project Manager

dberger@owasa.org

919-537-4240


-----------------------------------------------------------------


Meeting Summary

OWASA Community Meeting: West Rosemary Street Water Main Replacement Project

September 30, 2025

 

The following is a summary of the information presented and discussed at the September 30 public meeting.

 

  • The project is expected to take 18 months to complete, starting in late October/early November 2025.

 

  • The project will be primarily completed in eight sections from west to east. Temporary paving will be put in place after each section is completed; final paving will take place at the end of the 18-month project.

 

  • When each customer is connected to the temporary water main, and later to the new water main, water service will typically be interrupted for a half hour to two hours. Longer service interruptions, lasting four to eight hours, will occur when major water lines, such as one serving a cross street, are connected to the new water main.

 

  • With one exception, construction will take place Monday through Friday from 7:00 a.m. to 7:00 p.m. For the area near the intersection of W. Rosemary Street and N. Columbia Street, construction will take place in the evenings and weekends outside of the University’s school year to mitigate disruptions to traffic.

 

  • Throughout the project, OWASA will provide weekly updates every Friday for the week ahead. These updates will be shared via email, on OWASA’s social media accounts, and on OWASA’s webpage. To sign up for project updates, complete this form.

 

  • During the project, W. Rosemary Street will be closed in both directions within the section under construction. Pedestrian access won’t be impeded, for the most part, including access to businesses. Street crossing will be limited within segments where construction is taking place.

 

  • Those who access driveways and parking lots/decks along the project corridor to will be accommodated by on-site construction staff to ensure that they can access their residence and/or business. Residents/employees will be allowed to drive into the project area and access their driveway or parking deck. At times, it will take a couple of minutes for on-site workers to prepare the way for access.

 

  • When there are planned water outages during the project, notices will be provided 48 hours ahead and delivered via Everbridge to the contact information associated with the property’s OWASA account. If you rent and/or do not pay your bill directly, and therefore your contact information isn’t associated with the OWASA account, you can sign up for OC Alerts to receive planned and unplanned water outage notifications. Sign up for OC Alerts here. (Be sure to subscribe to OWASA Alerts under “Non-Emergency Alert Subscriptions".)

 

  • OWASA’s contractor, Moffat Pipe, will work closely with other utility providers to minimize service disruptions due to the construction.

 

  • If special accommodations are needed during the week to ensure access to a parking area (e.g. funeral services), please contact the Moffat Pipe Senior Project Manager (contact information below). Please provide advance notice when accommodations are needed. Parking lot access for weekend services will not be affected.

 

  • OWASA’s contractor, Moffat Pipe, will be making accommodations during major University sporting events to minimize traffic disruption.

 

Key Contacts

 

Questions about overall project and timeline

Project Manager, OWASA

Darren Berger

dberger@owasa.org

919-537-4240


Questions about updates and outreach

Public Information Officer, OWASA

Katie Hall

khall@owasa.org

919-537-4236


Questions about construction schedule and concerns on-site

Brad Keeley

Senior Project Manager, Moffat Pipe

bkeeley@moffatpipe.com

919-710-5407