Week of July 27, 2026

Haga clic aquí para ver esta informacíon en español.

CANCELLED: Northbound McFadden Avenue Off-Ramp Extended Closure

The extended closure of the northbound SR-55 McFadden Avenue off-ramp, scheduled to begin on Tuesday, July 28, has been cancelled until further notice. Additional information will be provided in future communications.

Retaining Wall Construction

WHAT:

Crews are expected to perform paving activities along the retaining wall near the northbound (NB) McFadden Avenue off-ramp. This work will require closing the NB McFadden Avenue off-ramp, Edinger Avenue on-ramp, and two outside lanes between these ramps.


WHEN:

9 p.m. to 5 a.m. nightly, Monday, July 27 through Thursday, July 30.


This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Closures and Detours Map

Bookmark the closures and detours map for quick access to real-time construction information. Click on the construction icons to view activities and closures.

About the Project

OCTA, in cooperation with Caltrans, is improving 4 miles of SR-55 between I-405 and I-5. The project will improve traffic flow and reduce travel time by adding one regular lane and one carpool lane in each direction. Also, the project will add merge lanes between several interchanges and stripe carpool lanes for continuous access, augmenting safety on the freeway by making merging easier. These enhancements are expected to create a better, smoother driving experience for motorists.

 