The Development Construction Manager has updated the Association on the road construction they will be working on within Wendell Falls through this week and the next.

Asphalt pouring | a top coat of asphalt will be installed. This work will begin July 22 and weather permitting should be finished by July 25.

  1. Alley off Douglas Fall (lots 1041-1066)
  2. Alleys between Big Barn and Douglas Falls (lots 1067-1071 & 1072-1091)
  3. Stagecoach Trail
  4. Noble Deer Way
  5. Hidden Shadow Ln
  6. Colonial Berry Dr
  7. Big Barn Dr
  8. Taylor Rd ( from Cardinal School to just past Noble Deer Way)
 
The estimated schedule, weather permitting, are streets 1-3 (possibly 4) paved tomorrow, June 22 and streets 4-8 paved on Monday June 25 . 