West Avenue Phase 2 Project Advisory

Intersection Closure and Detour Extended West Avenue at 17 Street for New Infrastructure Installation

Project update sent: August 2, 2024

 

What’s New 

The intersection of West Avenue and 17 Street will remain closed for an additional few weeks while the contractor continues installing pipe for the new watermain and pump station outfall. The contractor is expected to move into the next part of the work along southbound West Avenue between 17 Street and Lincoln Road in mid August.

 

Watermain and the outfall pipe installation is in progress from the pump station site within the City-owned parking lot at 1671 West Avenue (next to the U.S. Post Office) to the green space on the northwest corner of West Avenue and 17 Street. 


Work at Intersection of West Avenue and 17 Street

Within Segment 1 of the West Avenue Phase II project, roadwork was divided into five parts and is expected to take several months for completion. Work at this intersection (part 2 of 5) is scheduled into mid August. This includes the closure of the intersection of West Avenue and 17 Street. A detour will be established to guide drivers around the area. Access will be maintained for local businesses and pedestrians throughout the area.


Drivers traveling north on West Avenue, wishing to continue north can use Lincoln Road and Alton Road. Drivers traveling along Dade Boulevard will be directed to use Alton Road to travel around the work. Alton Court will remain open.


Additional updates will be distributed to provide notice on the remaining parts of work and any associated lane closures. Please follow all posted signs for speed limit, lane closures and detours.


Project Overview and Benefits

The project’s critical upgrades represent a comprehensive neighborhood improvement program, focused on resolving challenges associated with climate impacts and aging infrastructure. The proposed improvements within the West Avenue neighborhood include replacement of the existing water distribution/transmission systems and gravity sanitary sewers; installation of a robust storm water drainage collection and pumping system, including the raising of the paved roads, sidewalks and harmonization within the adjacent private properties; installation of street and pedestrian lighting; installation of new traffic signals and mast arms; installation of landscaping and irrigation; and construction of a segment of new Baywalk.


Pump Station Work

The parking lot will remain fenced and closed as work continues. All construction associated with the pump station is anticipated to last approximately two years. Please note, this schedule may change due to weather or unforeseen circumstances.

Next Steps

The underground utility and roadway work within the West Avenue neighborhood is being scheduled. A pre-construction public meeting will be conducted prior to the start of neighborhood work for Segments 2 through 9. Thank you for your continued cooperation throughout the West Avenue Phase 2 Neighborhood Improvement Project. 


Contact

Should you have any questions regarding this project, please contact:

Heather M. Leslie, Public Information Liaison, email: heather@hmlpublicoutreach.com

To learn more about the city’s innovative initiatives, visit www.mbrisingabove.com


To request this material in alternate format, sign language interpreter (5-day notice required), information on access for persons with disabilities, and/or any accommodation to review any document or participate in any city-sponsored proceedings, call 305.604.2ADA (2232) (voice), select 1 (English) or 2 (Spanish) and leave a message with your request. TTY users may call via 711 (Florida Relay Service). You can also make requests online at www.miamibeachfl.gov/ada by selecting ADA request.