Mill Street Reconstruction Project

July 9, 2025

 

You may see saw cutters working throughout the project area as crews prepare sections for excavation. For your safety, please keep a safe distance—these tools can create dust, debris, and noise during operation.


As previously shared, Mill Street is now closed from Main Street to C Street through July 31. While work continues in this section, we will be constructing new sidewalks between E Street and H Street. 

 

Here's the current plan:

West Side (E Street to H Street):

  • Sidewalk area excavation begins this week.
  • Concrete pouring is planned for the week of July 14.

 

East Side (E Street to H Street):

  • Excavation is scheduled to begin the week of July 21.
  • Sidewalk installation will follow.

 

The contractor will coordinate any driveway closures directly with residents. If you have any questions, please contact construction superintendent Dustin Davies at 971-375-3406.


Thank you for your continued patience throughout construction. Please see the map below for updated detour and closure information.

Click the map for a larger view

 

Questions?

Contact:

Kristi Krueger, P.E.

Capital Engineering Manager

kkrueger@springfield-or.gov

541-726-4584

Dustin Davies

K&E Excavating

dustin.davies@keex.net

971-375-3406

 

Forward this email to other community members you know who may like to be informed about the Mill Street Reconstruction Project

They can use the above button to sign up to receive email updates automatically.

Staff will provide updates on the Mill St. reconstruction project webpage https://bit.ly/MillStreetReconstruction.

 

We will also send out electronic updates through email, if you were forwarded this email and want to receive these updates, please sign up using this link: https://bit.ly/MillStreetReconstructionEMAIL.

 
 
 
 
 
Facebook  Twitter  Instagram  Linkedin  Youtube