WHAT:
Crews are expected to demolish and reconstruct the center median on Katella Avenue/ Willow Street beneath the freeway.
The removal of the existing median is anticipated to occur over several nights followed by structural excavation for approximately one week. Nighttime median reconstruction is expected to continue through the end of July.
Construction activities may require intermittent on- and off-ramp closures or lane reductions on Katella Avenue. Motorists are encouraged to plan ahead.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
WHEN:
9 p.m. to 5. a.m. nightly, beginning as soon as Wednesday, July 9 and continuing through the end of July.
For more information, including closures and detours visit octa.net/605Construction.
|