SATURDAY WORK IN AUGUST: The demolition of Las Lomas Apartments east side (see site plan below) has begun. Crews will be working the next several Saturdays, August 5, August 12, and August 19 to haul material, debris, and dirt to an offsite location. Working hours on Saturdays will be 9:00am-5:00pm.
PROJECT SCHEDULE: July 31 - September 30, 2023 (Dates are subject to change with weather conditions.)
July 31: Mobilize equipment
August 1-28: Demolish structures
August 29 - September 1: Tree removal
September 4-15: Parking lot and lights removal
September 18-27: Rough grade site
September 28-29: Clean up and demobilize
WORK HOURS:
- Monday - Friday, 7:00 am to 5:00 pm (loud work will not begin until 8 am)
- Saturday: 9:00 am to 5:00 pm (advance notice will be given)
- Sundays and holidays: No work
ACCESS: Streets and sidewalks will remain open during this phase of the demolition project. Future phases will require closures, which will be announced in advance. Please follow any traffic control measures during the project and use caution when traveling in the area during demolition.
WHAT TO EXPECT DURING DEMOLITION: Residents can expect the following impacts during construction:
- Heavy equipment
- Noise, dust and vibrations
- Odors
- Increased truck and equipment traffic
- Please stay away from construction areas and equipment to ensure the safety of all residents.
CONTACT: For questions or concerns, please contact Michael Morrell, UCI Design and Construction Services, at m.morrell@uci.edu. We appreciate your cooperation and apologize for any inconvenience this may cause.
Click here for UCI Environmental Review. For more background and information about the Area 12 project, go to: icha.uci.edu/Area12
|