Sherwood Boulevard Roadway and Drainage Improvements
Sherwood Boulevard is closed to thru traffic for road and drainage work. Crews with Star Paving Company will continue road and drainage improvements on Sherwood Blvd. between Piedra Loop and Aztec Ave.
Currently, crews are removing curb and gutter, selected driveways and have begun trenching for installation of a storm drain requiring Sherwood Blvd. to be closed to thru traffic from Grand Canyon Dr. to Aztec Ave. Sidewalks will be closed and barricaded to pedestrians. Traffic devices and detour signs are in place to help motorists, bicyclists and pedestrians navigate around the work zone. Pedestrians may utilize Atomic City Transit while sidewalk closures are in place. Vehicular access is limited to those who reside in the immediate work area and to mail delivery, emergency services, trash, and recycling collection. For safety of the traveling public, residents are asked not to or remove or relocate traffic control devices, signs, and barricades. Area residents who may have special access needs are asked to contact the Public Works Department.
Closure of Sherwood Blvd. from Grand Canyon Dr. to Aztec Ave. for this first phase of work is scheduled through the end of June 2022, while closure for the next phase of roadwork from Piedra Lp. to Grand Canyon Dr. is scheduled for June to July 2022.
In addition, Bixby Electric is working at Piedra Lp. and Sherwood Blvd. installing a new streetlight at the intersection.
Work schedules are subject to change pending weather conditions and any material shipping delays. Work Hours are 8:00 a.m. to 5:00 p.m. Monday through Friday.