Greenwood Drive Phase 2 Roadway Construction Begins Tomorrow 12/5 at 8 AM
December 4, 2019
Please read this important update from Sea Pines CSA regarding the roadway reconstruction of Greenwood Drive from Governors Road to Plantation Drive intersection.

Key Messages:
  • Road construction on Greenwood Drive, from Governors Road to Plantation Drive intersection begins tomorrow 12/5/19 at 8 am.

  • Work will be performed Monday-Friday from 8 am-5 pm with flag persons present to control traffic with alternating single lane closures in the designated work zone.

  • Please observe and obey all traffic management personnel, signage and devices.

  • Motorists should expect traffic delays. To avoid the project area, please use the Ocean Gate.

Project Zone:
  • Greenwood Drive from Governors Road to Plantation Drive Intersection
  • Erosion control and tree protection have been installed along the project work zone.

Current Status:
  • This area of Greenwood Drive is in need of infrastructure repairs and reconstruction
  • The useful life of this roadway has exceeded the initial design
  • The existing pavement is in poor condition

Project Goals:
Reconstruction of Greenwood Drive from Governors Road to Plantation Drive to include:
  • Stabilize roadway to extend road life
  • Replace curbing at necessary locations
  • Improve traffic flow and safety
  • Improve and increase drainage efficiency
  • Reconfigure the intersection at Plantation Drive and Greenwood Drive to improve safety
  • Replace Pedestrian and Vehicular Guardrails near Six Oaks Cemetery

Phase 2 Traffic Management Plan:
  • Work will be performed Monday-Friday from 8 am-5 pm with no work occurring on major holidays. Saturday work may be necessary, but will be communicated in advance.
  • During work times, we will employ alternating single lane closures on the portion of Greenwood Drive, from Governors Road to Plantation Drive. Flag persons will be present to control traffic.
  • Signage has been placed throughout the work zone and at various locations within the community, to communicate project messages.
  • Motorists should expect traffic delays. The project area is considered an active work zone. Please use caution while in driving in this area. To avoid the project area, please use the Ocean Gate.
  • Please observe and obey all traffic management personnel, signage and devices.

Phase 2 Traffic Management Plan Diagram:
Communications from Sea Pines CSA:
How to stay updated regarding this project ….



Questions?
If you have questions regarding this project, please contact the Sea Pines CSA Maintenance Department at 843.671.7849, or email csamaintenance@csaseapines.com .

Thank you for your patience, as we make these necessary infrastructure and safety improvements to Greenwood Drive.