Please see the below updated fee increase in West Henderson related to: Henderson Municipal code Section 14.18.045 - West Henderson Phase 1 Water Backbone Infrastructure Rates.
The city has concluded that the backbone infrastructure should be constructed in a single phase by the city and that the rates charged to the projects benefitting from the infrastructure need to be increased.
Effective January 1st, 2023, all new projects that the City determines will receive a benefit from existing or future water backbone infrastructure planned, designed, constructed, and/or financed for West Henderson 2630 Pressure Zone or for the 2760 Pressure Zone shall be charged and pay the approved rates.
- 2630 PZ water infrastructure Rate: $3,527 per EDU
- 2760 PZ water infrastructure Rate: $5,660 per EDU
There were also changed to the Commercial and Industrial Meter Equivalency Chart that will go into effect January 1st, 2023.
- Table with new fee changes below: