Crews with the Missouri Department of Transportation and its Design-Build team set the first bridge girders associated with the Improve I-70 Program on Feb. 25.
The first project of the program will add a third lane to each direction of Interstate 70 along the 20-mile stretch between Columbia and Kingdom City. It also includes I-70 interchange improvements at U.S. Routes 63 and 54.
The recently placed girders are part of a new southbound U.S. Route 63 bridge that will create a brand-new underpass along the route at Conley Road and will provide more local connectivity to businesses on each side of U.S. 63.
Improve I-70: Columbia to Kingdom City is a $405 million fixed-cost contract and is the first of several projects that will expand and improve I-70 across the state. This project is scheduled to be completed by the end of 2027, with total program completion anticipated by the end of 2030.
To learn more, visit the Improve I-70 Program website.
|