The Jackson Creek Parkway Widening Project (Higby Road to Highway 105) is part of the Town of Monument’s overall improvements program designed to address community needs and desires for the entire corridor that will also accommodate existing and future development. Design of the “ultimate” roadway widening improvements is underway by the engineering firm of FHU. A construction schedule has not yet been set as the town is working to pursue construction funding.


The widening project specifically involves expanding Jackson Creek Parkway from one lane in each direction to two lanes in each direction, extending the four-lane configuration from Higby Road north to the intersection of Highway 105. Plans also include a raised median, and associated left and right turn lanes and signalization designs at all required intersections. Drainage improvements, median landscaping, sidewalks on both sides of the road, pedestrian and bike pathways, and “Gateway” treatments are also part of the project design.



Several other projects are taking place along or adjacent to the Jackson Creek Parkway corridor and in some cases will overlap with the widening project.  The Town of Monument and the Jackson Creek Parkway Widening Project team are coordinating with other jurisdictional entities and private developers to minimize public inconvenience as much as possible during construction.

Pictured above is a schematic design of the future Jackson Creek Parkway Widening Project

Monument Junction Project D (On Jackson Creek Parkway between Highway 105 and just north of Slopeside Street):  



Anticipated completion: Fall 2025



Construction by the Monument Junction Metro District’s contractor, Wildcat, is underway to support the Monument Junction development. This is the ultimate build out of the intersection at Jackson Creek Parkway & Highway 105. The Jackson Creek Parkway Interim work previously completed was tied directly to Monument Junction for access to both.

Pictured above are traffic delineators at the intersection of Highway 105 and Jackson Creek Parkway.

Construction Status:

Watch for trucks entering/exiting the construction area and for reduced speeds during construction. Use caution in the construction zone.

  • Traffic delineators are now installed on Highway 105 replacing the barrels eastbound for the right turn southbound on Jackson Creek Parkway
  • Concrete barriers are installed on the eastbound side of Jackson Creek Parkway

 

Phase 1 construction:

  • Utility Work on Highway 105 east of Jackson Creek Parkway
  • Major fiber duct lowering is in progress at the Lumen Central Office
  • Black Hill Energy gas relocation is completed
  • Mountain View Electric line relocation is completed
  • Woodmoor sanitary sewer line relocation will take place in the coming weeks after the Lumen fiber duct lowering is completed
  • Retaining wall construction on the east side of Jackson Creek Parkway and Highway 105 will start after the completion of the utility relocation
  • Signalization at Fat Tire Drive
  • Storm sewer work on Highway 105

Pictured above is utility work underway on Highway 105, east of Jackson Creek Parkway.

Phase 2 construction:

  • Jackson Creek Parkway northbound dual left turn lanes onto Highway 105
  • Highway 105 westbound dual left turn lanes onto Jackson Creek Parkway
  • Highway 105 eastbound right turn lane onto Jackson Creek Parkway
  • Traffic signalization


Map of Project D

Monument Junction Project D improvements on Jackson Creek Parkway and Highway 105 are depicted on the map in yellow.