WHAT TO EXPECT WITH PHASE 2: Back of Gym
-
Projected Start Date: Mid-October 2023
-
Estimated Duration: Approximately 10 weeks
-
Anticipated Opening: January 2024 (🤞)
1. WEIGHT ROOM | Renovations Start: October 9
We're making some exciting changes to our weight room area.
The current weight room space will undergo a complete makeover, resulting in a more spacious weight training and cardio area, along with the introduction of an expansive, brand-new Yoga Studio and group fitness area.
Changes will begin with the Moonboard, which will be removed and sold to make room for these facility upgrades. Upon completion of our renovation, we'll introduce (2) new training boards; a Kilter and Tension 2 board. In addition, (2) new training boards will be installed at BRB; an all-new Moonboard and a second Kilter board. Please be aware that we will be without a training board for a couple of months. We greatly appreciate your patience as we create an enhanced training experience for you.
Additionally, please note that during this time, the fitness and cardio equipment will be temporarily unavailable. We apologize for any inconvenience this may cause and will do what we can to make creative use of available spaces to help minimize further disruptions to your fitness routines.
See: ‘3. Pirate Ship + Instruction Wall’ for more details about the
new weight room and cardio area.
2. LOCKER ROOMS + BATHROOMS | Renovations Start: October 12
Our locker rooms are getting a well-deserved makeover.
We will be demolishing the existing locker rooms and bathrooms to make way for an all-new, expanded and updated men's locker room, complete with a sauna. (The all-new women’s locker room with sauna will be located in the new expansion area; both are projected to open at the same time.)
To ensure your convenience during construction, we will be bringing in temporary bathroom trailers with the same number of toilets as before, including ADA facilities. While these restrooms will have running water (flushable toilets and functional sinks for hand washing), showers will not be available during this time. Please come dressed to climb.
During this period, the current water fountain will also be taken out of service, but a temporary water cooler will be provided.
3. PIRATE SHIP + INSTRUCTION WALL | Renovations Start: October 13
We remain committed to helping young climbers discover, learn and excel at climbing.
Just as we structure our Youth Programs, we believe that the young climbers in our community should have equal access to our climbing walls, routes, and holds. This approach works to develop them both as climbers and as integral members of our climbing community.
As we embrace these exciting changes, it will soon be time to bid farewell to the Pirate Ship and instruction wall, allowing us to create room for an entirely new weight training and cardio area equipped with new treadmills, ellipticals, weight racks, benches and more.
Nearby, the all-new mezzanine in the expansion space will feature the Kilter and Tension boards, hang boards and campus boards.
4. ACCESS TO THE SOUTH BAY | Remains Open
Ensuring continued access to the South Bay bouldering walls is a top priority and will continue to be maintained throughout the renovation process, though access points may change. Please keep an eye out for signage that will help guide you in the right direction.
|