We honor and thank all who have served our country. In observance of Veterans Day there will be no activities or closures on Wednesday, Nov. 11.

Upcoming SR-91 Closures

WHAT: Crews are expected to perform two nighttime westbound (WB) SR-91 directional freeway closures for demolition of the Lakeview Avenue bridge bent column footing. Drivers should plan for detours and allow extra travel time.


WHEN:

Westbound SR-91 Closures:

  • 9 p.m. Friday, Nov. 13 to 5 a.m., Saturday, Nov. 14
  • 11 p.m., Saturday, Nov. 14 to 7 a.m., Sunday, Nov. 15


Lakeview is also expected to close during these two overnight periods, from 10 p.m. to 5 a.m.


WHY: These closures are necessary to safely complete the second phase bridge demolition and protect motorists and construction crews.

CLOSURES:

  • WB SR-91 freeway under the Lakeview Avenue bridge between Imperial Highway and the SR-55 Interchange
  • Lakeview Avenue between Riverdale Avenue and Santa Ana Canyon
  • WB SR-91 on- and off-ramps at Lakeview Avenue
  • WB SR-91 Express Lanes (SR-55 to the County Line)

This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Segment 1: Lakeview to SR-55

Lakeview Avenue Bridge Construction

Crews removed all ten girders from the superstructure during two weekends of demolition on the old half of the Lakeview Avenue bridge. Demolition of the bridge abutments is expected to continue during daytime hours. Crews are also expected to remove the remaining bent column footing during nighttime hours next weekend. Intermittent nighttime work, Lakeview Avenue closures, and SR-91 freeway lane closures will continue as crews complete demolition and transition into the next phase of construction.


Reminder: Pedestrian access across the bridge is currently closed. As early as mid-November, the sidewalk on the east side is expected to reopen. The sidewalk on the west side will remain closed while crews continue construction activities.


Daytime soundwall work is ongoing and is expected to be complete in late 2026.


For a full list of weekly closures and detours, and the most up-to-date project information, please click on the project Google Map below.

Crews removing rebar and demolishing the old half of the Lakeview Avenue bridge.

This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Click Here to Learn More About Lakeview Avenue Bridge Construction

Segment 2: SR-55 to SR-57

Construction on Segment 2 of the SR-91 Improvement Project is expected to begin in early 2027.

Segment 3: SR-57 Interchange

Crews will continue roadway, drainage, and electrical improvements throughout the Segment 3 construction zone. Upcoming work includes traffic control implementation, roadway excavation and embankment construction, concrete and asphalt pavement removal, drainage pipe and inlet installation, roadway base preparation and fine grading, concrete paving, and temporary lighting and fiber installation. Work is scheduled during both daytime and nighttime hours.


For a full list of weekly closures and detours, and the most up-to-date project information, please click on the project Google Map below.

Crews performing roadway excavation, preparing concrete pavement for construction, and moving excavated materials throughout the Segment 3 construction zone.

This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

State College Boulevard Construction Activities

The SR-91 bridge over State College Boulevard is being widened to improve traffic flow and safety. Crews are scheduled to continue work on the bridge abutments, with additional abutment-related activities tentatively scheduled for the coming weeks. The schedule for this work is subject to change. Motorists should check project updates for information about upcoming closures and traffic impacts.


For the latest construction information, traffic impacts, and closure updates, visit the project's Google Map and monitor future construction alerts.

Crews performing roadway excavation, removing existing materials, and preparing the construction area for roadway improvements at State College Boulevard.

This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

REMINDER:

La Palma Avenue Lane Reduction

One lane on EB La Palma Avenue is closed between Blue Gum Street and Frontera Street and will remain closed until further notice. Motorists may experience increased traffic and delays in the area. Please plan ahead, allow extra travel time and consider alternate routes if available.


For a full list of weekly closures and detours, and the most up-to-date project information, please click on the project Google Map below.

Learn more about planned improvements at octa.net/91Improvements.

Closures and Detours

Click here to view a full list of project closures.

For a full list of weekly closures and detours, and the most up-to-date project information, visit our closure list please click on the project Google Map below.

Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.

About the Project

91 Connect Business Program

The "91 Connect: Shop Local, Support Local" program supports businesses along the SR-91 Improvement Project corridor by promoting visibility and minimizing construction impacts through proactive outreach. Business spotlights on the project website, social media, and construction alerts, are all aimed to encourage the community to shop local and raise awareness of local businesses during construction. Click here to learn more.

Overview

The SR-91 (SR-57 to SR-55) Improvement Project will improve 6.6 miles of State Route 91 (SR-91) through Anaheim, Fullerton, Orange, Placentia and Yorba Linda. The project will improve mobility throughout the corridor, reduce weaving and merging between ramps, and improve on- and off-ramps. The project will reconstruct the La Palma Avenue, Kraemer Boulevard/Glassell Street, Tustin Avenue and Lakeview Avenue bridges and interchanges with standard lanes, shoulders and sidewalks in each direction. Visit our website for more information on segment and schedule details, octa.net/91improvements.

Click here to see all the project resources, renderings, and factsheets.

If your community or organization is interested in receiving a project presentation or briefing, please email the Outreach Team at 91Project@octa.net.

STAY CONNECTED

Facebook  X  Instagram

888-280-7966

91Project@octa.net

octa.net/91Improvements

Text SR91PROJECT to 877-676-4182 to sign up for text alerts.

 