Exciting progress is underway across our campus!
- Picnic Pavilion & Restroom Facility
The metal pavilion structure is fully erected, with roofing complete. Restroom masonry and trusses are in place, and interior work is ongoing through May. Exterior siding and stone veneer will continue into the month.
The foundation and slab are done. Masonry work continues through April, steel erection through May, and roofing into June. Interior framing begins in July, with finishes starting once the building is fully enclosed in August.
The pool shell is complete, with plumbing and slab work progressing. Final finishes are scheduled for October - November.
- Sitework & Civil Improvements
Major utilities are finished. Grading, paving, and lighting are planned for July - October, with sidewalks and fencing in August, and final signage by mid-October.
We’re excited to watch these spaces take shape - creating even more opportunities for recreation, relaxation, and connection at Moosehaven!
|