It’s mid-July, and while things might be a little quieter than usual in the neighborhood around Tufts Street with classes out for the summer at the East, Capuano, and WHCIS at Edgerly, we’re moving toward the start of construction.
Tree removal work is here while sidewalk reconstruction will have to wait a bit longer as our contractor’s crews complete remaining work elsewhere in the city and beyond.
Below we’ve included some details on tree removal work and what you can expect moving forward.
Tree Removals (and info on future plantings)
Last week crews began removal of the 21 street trees slated for removal as part of this project. These trees were assessed by the City’s Arborist and Tree Warden and approved for removal at a public tree hearing in November 2024.
The good news is that the City will be planting around ~40 new street trees as a part of this project. The new, wider sidewalks will allow us to plant these news trees in larger, continuous planting areas that promote heathier growth. (The majority of the trees slated for removal were in poor to fair health due in part to them having been planted in smaller tree pits).
New trees will create continuous shade coverage along the street and species are selected by the City’s Urban Forestry Division.
What's Next?
Drainage work in advance of sidewalk reconstruction is currently anticipated to begin in early September after the Labor Day holiday. As this work approaches, we’ll share more information with the neighborhood about the contractor’s plans and a more specific schedule.
For more info on this work including an overview of the project's design, visit our project website.
|