August - Construction Update

Welcome back to the City of Somerville's construction newsletter!

Street-level view of recently paved raised crossing, showing new asphalt without crosswalk marking

New raised crossing at the intersection of Tufts Street and Glen Street ahead of pavement marking

As we move into the second week of August, crews are hard at work installing new water mains on streets near the East Somerville Community School and Edgerley Building ahead of back-to-school at the end of the month. Meanwhile, just on the other side of McGrath Highway, work on the City's Western Pearl Street Reconstruction is getting underway.


Read on for more on both of these projects, as well as other work to improve our city's above- and below-ground infrastructure. If you have any questions about the work described in this email (or any work in the city) please don't hesitate to reach out to us at construction@somervillema.gov. 


What We're Sharing This Month: 


  • Western Pearl Street - Preliminary Drainage Work
  • Cross Street at Tufts Street Raised Crossing
  • Elm-Beacon Connector Quick Build Installation Gets Underway
  • East Somerville Water Mains
  • Subterranean Somerville - Sewer Cleaning and Inspections
  • Keeping up to date 
  • We can’t cover all the work in one newsletter 

Western Pearl Street Reconstruction and Safety Improvements

Blue and green map highlighting limits of the Western Pearl Street project from Medford ST. to McGrath Hwy

Project Limits (Medford Street to McGrath Highway) for the Western Pearl Street Reconstruction Project

Work to build a safer, more accessible Pearl Street between McGrath Highway and Medford Street is getting underway as crews begin preliminary drainage work at the easternmost end of the project area. Following drainage work, they’ll turn their attention to rebuilding the sidewalks while implementing a new street design in the process. 


The new street design will make traveling along the street safer and more comfortable for everyone whether they are walking, wheeling, biking, taking the bus, or driving.   

Illustration of new street design, highlighting elements such as a raised cross at Medford Street, new trees, and more.

Rendering of the new street design highlighting the Medford Street or western end of the project area.

See the full design here.

The new design includes: 


  • raised crossings and intersections  
  • new protected bicycle facilities  
  • improved bus stops  
  • new benches and street trees 
  • among other safety and accessibility improvements  


To learn more about the project, including details on the final design, and feedback from the community process, please visit the project page below.  

Elm-Beacon Connector

Quick-build Installation

The Elm-Beacon Connector is a quick-build project and does not involve major street reconstruction. However, it will bring major changes and improve safety on Elm Street and nearby segments of Somerville Avenue and Beacon Street.  


The project will primarily use pavement markings, signage, flex posts, and traffic signal upgrades to implement a new design and make the street safer. 


Implementation is currently underway as new signage is installed to indicate changes to parking—initial pavement marking is expected to begin later this month. 

View from Mossland facing Elm Street, purple road marking indicate bidrectional travel for cyclists. Two cyclists seen riding along the street.

Rendering of plans for the new Neighborway on Mossland Street at the intersection of Elm Street.

Highlights of the new design include:

  • Separated bike lanes on Elm Street, Somerville Avenue, and Beacon Street protected with a buffer and plastic flex posts.  
  • A new Neighborway on Mossland Street allowing north- and south-bound travel for people biking while dead-ending the section of Mossland Street at Elm Street for motor vehicles.  
  • Access will be maintained for emergency vehicles at both ends of the street. 
  • Clear Corners installation at all intersections to improve sight lines. 
  • New traffic signal equipment to allow smooth travel for all modes of transportation, including bus detection for more efficient public transit movement. 


The majority of implementation is expected to be complete by November. Regular updates on installation progress will be available on the project webpage at somervillema.gov/elmbeacon. 


Cross Street at Tufts Street - Raised Crossing Construction

As one of the final pieces of the Tufts Street Reconstruction project, crews installed a new raised crosswalk across Cross Street.

Construction crews stand over a partially dug up crossing on Cross Street.
A new raised crossing is seen from the corner of Cross and Tufts Street. Granite curbing is visable across the roadway and construction equipment is in the background.

The new raised crossing at Cross Street and Tufts Street in progress

Why a raised crossing?


Raised crossings are
traffic calming tools designed to make our streets safer and more comfortable for everyone. Since they are elevated (roughly to sidewalk height), people driving must slow down as they approach the crossing.


Because they are sidewalk height, they enable people using wheelchairs and other mobility devices to cross more easily.


Installation of remaining new signage and pavement markings are planned for the next 1-2 weeks and will mark the substantial completion of the project.

Water Utility Work Continues in East Somerville

Ensuring water mains remain in good working order is essential to the City’s ability to deliver clean water to residents and to ensuring that enough water is available at any given time for effective fire suppression.

An open trench (dug up portion of the street) is seen with construction workers standing above it and a new pipe being put into the ground.

City contractors in the process of installing a new water main.

Work to update water utilities began in East Somerville last fall and is currently ongoing on:


  • Everett Avenue
  • Brook Street 
  • Indiana Avenue
  • Ellsworth Street


Learn more about this work and see a full map of locations on the project website below.


Residents of affected streets will receive additional notification prior to work taking place.

Subterranean Somerville:

Inspecting and Cleaning Our Sewers

What is Subterranean Somerville?

Ever wonder what's under your feet when you cross Broadway to get to Foss Park? Or why we've been doing so much digging in Spring Hill?


Each month we'll use this space to highlight a different element of the world beneath our streets—the old, the new, and what it all means for the future of our city.

Take a trip into our city's sewers


This month crews will be out inspecting and cleaning a portion of Somerville’s over 180 miles of sewer pipelines. These pipes are a critical assets to our community that residents and businesses rely upon daily.


Just like any other infrastructure or equipment, our sewers require regular upkeep and rehabilitation in order to function effectively.

See how contractors use specialized equipment to both clean the pipes and gather video footage to help identify areas in need of repair.

Stay Up to Date on Citywide Construction Projects

There is a lot of work being done in Somerville as we look to modernize and improve our city’s infrastructure, and we can’t cover it all in one email.


Stay up-to-date with what’s going on in your neighborhood and around the city via the following channels: 




Have questions?

Get in touch

Want to learn more about these projects? Or have questions about work in your neighborhood?


construction@somervillema.gov

Language and Accessibility

To request translation or an interpreter in your language, please contact the Somerville Office of Immigrant Affairs at languageaccess@somervillema.gov or by calling 311.

ADA icon with four sections depicting ASL mobility TTY and CART services

Persons with disabilities can request accommodations to access the programs, activities, and meetings of the City of Somerville by contacting the ADA Coordinator at 617-625-6600 x 2059 or ADA@somervillema.gov in advance of the event.