Construction activities continue to move forward, with sidewalk and drainage work progressing in Phases 1A, 1B, and 2B. Phase 1A is also nearing completion.
As we look ahead, the project is preparing to shift into Phases 2A and 2B. Pending the opening of Phases 1A and 1B to the public, crews will begin demolition work in Phase 2B as early as mid-June, starting just south of the alleyway between Union Kitchen and Webster Bank. Additional work in this area will include soil-cell installation, curb construction, and sidewalk grading.
Keep an eye out for direct communications in the coming weeks.
Businesses located in Phases 2A and 2B include:
|