What's Happening
Construction on Pine Tree Drive at 51 Street for the force‑main replacement is ongoing. The contractor has begun tie‑in work, connecting the new 30‑inch sewer force mains to the city’s existing sanitary sewer system.
To complete this phase efficiently, some activities will take place during select overnight hours, scheduled as needed. These operations are an important step in upgrading the infrastructure and ensuring long‑term reliability of the service.
Traffic Changes
Lane closures are currently in place on both the north and south sides of the bridge on Pine Tree Drive near 51 Street. These closures reduce traffic to one lane in each direction and are expected to remain in effect for approximately 1–2 more months. Please find maps of the road reconfigurations on the north and south sides below.
South of 51 Street on Pine Tree Drive
- A short section of Pine Tree Drive just south of the 51 Street bridge is closed for the work zone. Southbound traffic is being routed into one of the northbound lanes, which has been temporarily reconfigured to provide one lane in each direction through this segment. Southbound vehicles will then transition back to the designated southbound lane beyond the work area.
|